BLD-Footing | 8/10/2020 | 8/11/2020 | 8/11/2020 | A | PASS |
Dave Hannah
|
|
|
8:30 AM pour time Phone #: ###-#### Inspection requested via web by bill gullickson
|
Issue PAID IN FULL permit | | | 8/10/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/10/2020 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/4/2020 | | |
|
|
|
Issue with Building D Foundation Only permit BLD20-02329 instead of BLD19-02196 as previously noted.
|
Expiration Notice | 7/23/2020 | 8/13/2020 | 7/23/2020 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 6/1/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 3/10/2020 | 3/10/2020 | 6/1/2020 | | DONE |
Rob Patrick
|
|
|
05/29 Resubmit ready to Pass after Planning Review: 2nd Review Complete 05/04 Failed: 03/27 L2 ePlan Townhouse
|
Routing - PLANNING | 6/1/2020 | | 6/1/2020 | | PASS |
David Moser
|
|
|
|
Routing - PLAN CHECK | 6/1/2020 | | 6/1/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/1/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 6/1/2020 | | DONE |
|
|
|
DO NOT ISSUE WITHOUT BLD20-02329 AND 20-00638 & 00738 - 00740
|
Plan Reviewer's activity | | | 5/29/2020 | | |
|
|
|
05/29 Bldg Review is complete and ready to PASS. Waiting for Planning review.
|
Routing - PLAN CHECK | 5/4/2020 | | 5/4/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Require
|
Plan Reviewer's activity | | | 5/1/2020 | | |
Rob Patrick
|
|
|
These 4 townhouses are ready to Fail pending Mechanical and Planning reviews.
|
Routing - PLANNING | 5/1/2020 | | 5/1/2020 | | FAIL |
David Moser
|
|
|
Need to provide letter from Idaho Power in regard to powerlines along alley. Provide a letter (email) from Boise Greenbike about bike hub location and Boise City Arts and History Department in regards to art piece
|
Routing - MECHANICAL | 5/1/2020 | | 5/1/2020 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 3/25/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - PLAN CHECK | 3/10/2020 | | 3/25/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - PLANNING | 3/10/2020 | | 3/24/2020 | | FAIL |
David Moser
|
|
|
Need landscape plan for the project this includes street trees along 28th street. Need to show location of bike parking and Greenbike hub. include letter from Boise Greenbike approval of Hub location. Need to provide letter Boise City Arts and History concerning the art at the intersection of 27th and Stewart. Need letter from Idaho power regarding power lines along ally.
|
Routing - PUBLIC WORKS | 3/10/2020 | | 3/13/2020 | | PASS |
Candy A. Nichols
|
|
|
TOWNHOUSE
|
Route to Impact Fee Review | 3/10/2020 | 3/13/2020 | 3/11/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 3/10/2020 | | 3/11/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 3/10/2020 | | 3/11/2020 | | FAIL |
Troy James
|
|
|
Emailed correction to applicant.
|
Plans ACCEPTED BY PLAN TECH | | | 3/10/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/10/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/10/2020 | | DONE |
|
|
|
|
Application received | | | 2/25/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 25 2020 9:44AM
|