Second Notice | | 7/19/2020 | 7/31/2020 | | DONE |
|
|
|
This permit finaled on the web by Charlene Meadows
|
First Notice | 6/16/2020 | 6/16/2020 | 7/9/2020 | | DONE |
Dave Hannah
|
|
|
mailed 7-9-2020
|
Letter of compliance/Occupancy | | | 6/22/2020 | | DONE |
|
|
|
|
BLD-Final | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by James Hibbard
|
DOC - Permit Finaled | 6/16/2020 | 6/16/2020 | 6/16/2020 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection is complete, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work is complete, signatures provided on permit sign off card.
Phone #: ###-#### Inspection requested via web by James Hibbard
|
FIRE-Final Inspection | 6/15/2020 | 6/15/2020 | 6/15/2020 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, rescheduled for 16JUNE2020 too coincide with fire alarm inspection.
Phone #: ###-#### Inspection requested via web by James Hibbard
|
BLD-Ceiling Grid Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | PASS |
Dave Hannah
|
|
|
Inspection requested via web by James Hibbard
|
BLD-Framing/Rough-in | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by James Hibbard
|
Issue PAID IN FULL permit | | | 4/22/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/22/2020 | | DONE |
|
|
|
|
1st review completed | | | 3/3/2020 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/3/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 3/3/2020 | | DONE |
|
|
|
All Met (brandon@ekconstruction.com)
Need
GC Form
Revised Cert of Value
|
Plan assigned to (M_H) | 2/28/2020 | | 3/3/2020 | | DONE |
Michael Hanson
|
|
|
03/04 L1 Ada county operations ePlan
|
Routing - PLAN CHECK | 2/28/2020 | | 3/3/2020 | | PASS |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 2/28/2020 | | 2/28/2020 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 2/27/2020 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 2/26/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 26 2020 11:26AM
|