BLD-Framing/Rough-in | 7/13/2020 | 7/14/2020 | 7/14/2020 | A | PEND |
Mike Jordan
|
|
|
screened - bolt // Shane Phone #: ###-####. Bolts are in snug tight condition, all plys are in conact. 3rd part inspection required to complete turn of the nut method per plans.
|
BLD-Foundation | 7/6/2020 | 7/7/2020 | 7/7/2020 | P | PART |
Mike Jordan
|
|
|
Shane SCREENED Phone #: ###-####. Work in progress on slab on grade and perimeter curb. Ok to place concrete pending special inspection.
|
BLD-Footing | 6/25/2020 | 6/26/2020 | 6/26/2020 | P | DEFR |
Mike Jordan
|
|
|
Shane - Pour time at noon Phone #: ###-####. Ok to place concrete pending special inspection.
|
BLD-Footing | 6/24/2020 | 6/24/2020 | 6/24/2020 | P | PASS |
Mike Jordan
|
|
|
Shane Phone #: ###-####. Column pad footings on gridline A, against existing building.
|
BLD-Footing | 6/18/2020 | 6/19/2020 | 6/19/2020 | P | DEFR |
Mike Jordan
|
|
|
Shane Pour time at 1 Phone #: ###-####. Ok pending special inspection.
|
BLD-Footing | 6/4/2020 | 6/5/2020 | 6/5/2020 | A | CANC |
Mike Jordan
|
|
|
Shane Phone #: ###-####
**CANCEL PER SHANE**
|
Place hold on job | 6/2/2020 | | 6/4/2020 | | DONE |
Gabe Brenner
|
|
|
no inspections until signed permit returned. not released in eplan
|
Print Occupancy Form | | | 6/2/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/22/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 5/8/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 5/8/2020 | | PASS |
|
|
|
All met! Email permits to mailto:shaun@gaffordconstruction.com
NEED
GC
REV Values
|
OVERRIDE | | | 5/5/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 5/5/2020 | | DONE |
|
|
|
NEED
GC
REV VALUES
|
Plan assigned to (J_N) | 3/16/2020 | 3/16/2020 | 5/4/2020 | | DONE |
Jenny Nelson
|
|
|
1st complete 04/15 - 502 Idaho Power Wash Bay Addition
|
Routing Off Site - STRUCTURAL | 5/4/2020 | | 5/4/2020 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/4/2020 | | 5/4/2020 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/2020 | | DONE |
Jenny Nelson
|
|
|
|
Routing PW Street Lights | 4/29/2020 | | 4/29/2020 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Drainage | 4/29/2020 | | 4/29/2020 | | PASS |
Jason C. Taylor
|
|
|
See notes on plumbing sheets. Jason Taylor ###-####
|
Routing - Design Review | 4/28/2020 | | 4/28/2020 | | PASS |
Michaella Owens
|
|
|
|
Route to Impact Fee Review | 4/17/2020 | 4/20/2020 | 4/20/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 4/17/2020 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 3/16/2020 | | 4/17/2020 | | FAIL |
Jenny Nelson
|
|
|
|
Routing PW Sewer Design | 3/16/2020 | | 4/17/2020 | | PASS |
DeAnn Brown
|
|
|
Wash bay shown connecting to wet line sewer.
|
Routing - FIRE | 3/16/2020 | 3/16/2020 | 4/16/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
Routing PW Drainage | 3/16/2020 | | 4/14/2020 | | FAIL |
Jason C. Taylor
|
|
|
See changemarks in ePlan. JCT
|
Routing PW Street Lights | 3/16/2020 | | 4/13/2020 | | FAIL |
Tom Marshall
|
|
|
|
Routing - Design Review | 3/16/2020 | | 4/13/2020 | | FAIL |
Michaella Owens
|
|
|
asked for parking spots to be shown on site plan before approving
|
Routing PW Environmental | 3/16/2020 | | 4/13/2020 | | PASS |
Zach Conde
|
|
|
per Zach:“Approved with sand and oil interceptor as shown.”
|
Plan Reviewer's activity | | | 4/10/2020 | | DONE |
Jenny Nelson
|
|
|
Was not routed to PW in ePlan. Routed to all required PW reviews on 4/10/20. JJN
|
Routing PW Solid Waste | 3/16/2020 | | 4/10/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing Off Site - STRUCTURAL | 3/16/2020 | | 4/10/2020 | | FAIL |
|
|
|
AHJ
|
Routing - PLANNING | 3/16/2020 | | 3/18/2020 | | PASS |
Nicolette Womack
|
|
|
Allowed use, requires DR.
|
Routing - Erosion and Sediment | 3/16/2020 | | 3/17/2020 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Idaho Power RP listed. Site preparation notification required.
|
Routing - Addressing | 3/16/2020 | | 3/16/2020 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/16/2020 | | 3/16/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - PLUMBING | 3/16/2020 | | 3/16/2020 | | PASS |
Daryl Spivey
|
|
|
Install a 2 inch vent downstream of SOI-1
|
Intake Approval | | | 3/5/2020 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 2/28/2020 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
1. As this is a new structure Provide a completed 502 checklist and 502 application. Both can be found at https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/commercial-construction-500/502-new-commercial-and-commercial-additions/
2. The 502 checklist is not complete unless all information is filled out, all appropriate boxes are checked and all plan page numbers are listed.
3. Provide items that are requested from the 502 checklist that apply to the project.
4. It was noticed special inspection is required revise uploaded 310 form to reflect items to be inspected
5. Revise uploaded ComCheck on sheet E0.02 to reflect the current adopted 2015 IECC not the 2009 IECC
6. Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on plan sheet AS2.01 see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
7. Provide into the drawing file the RM engineered plans that are uploaded in the document file. With that said the RM plans shall be 18” x 24” minimum, individually uploaded and reserve the bottom right corner for the city stamp. (what we have allowed is on an architectural plan sheet place anywhere from 2 or 3 of the pre engineered building sheets so that they can be 18” x 24” minimum and reserve the bottom right corner for the city stamp)
|
Application received | | | 2/27/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 27 2020 9:42AM
|