BLD-Framing/Rough-in | 7/23/2020 | 7/24/2020 | 7/24/2020 | A | PASS |
Brandon Shaw
|
|
|
Can you give me an hour heads up as I am running 2 jobs? Phone #: ###-#### Inspection requested via web by Jimmie Miller
|
Issue PAID IN FULL permit | | | 6/26/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/26/2020 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 6/23/2020 | | DONE |
|
|
|
MET Tim Keller
NEED
GC FORM
REVISED VALUE
|
Plan assigned to (M_H) | 5/27/2020 | | 6/23/2020 | | DONE |
Michael Hanson
|
|
|
1st review completed - 06/01 #518 L2 ePlan - St Luke's Laundry Facility
|
Routing - Design Review | 6/22/2020 | | 6/22/2020 | | PASS |
Katelyn Menuge
|
|
|
|
Route to Impact Fee Review | 6/5/2020 | 6/8/2020 | 6/8/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 5/27/2020 | | 6/5/2020 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 6/5/2020 | | DONE |
Michael Hanson
|
|
|
|
Routing - Design Review | 5/27/2020 | | 6/1/2020 | | FAIL |
Katelyn Menuge
|
|
|
Zoning Appeal Period Ends 6-5-20 @ 5pm.
|
Intake Approval | | | 5/26/2020 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 5/13/2020 | | FAIL |
Jenny Nelson
|
|
|
1. Per requirements of submittal checklist all plans must be drawn to scale on minimum 18x24 sheet size.
- Floor plan and site plan must be drawn to scale, on minimum 18x24 sheet size and stamped by design professional.
- past plans cannot be used without written consent from architect - also as designed under previous building code year can only be used for reference.
2. Per submittal checklist requirements all zoning approvals must be completed prior to building department intake approval, please upload approved zoning certificate.
|
Intake Approval | | | 4/17/2020 | | FAIL |
Jenny Nelson
|
|
|
To complete your application please provide the following:
1. Please provide everything required on submittal checklist
- 304 registered design professional form
- code analysis/building data
2. Per requirements of submittal checklist all plans must be drawn to scale on minimum 18x24 sheet size.
3. Per planning and zoning staff, a Zoning certificate will be required to be completed prior to a building permit as this is an exterior alteration - please contact planning and zoning for requirements to complete zoning certificate.
|
Intake Approval | | | 4/1/2020 | | FAIL |
Jenny Nelson
|
|
|
1. A completed submittal checklist which can be found on the city website: https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/?category=commercial%20construction%20-%20500&search=all
2. As there are exterior changes to this building you will need to talk to planning and zoning first as it may require a design review application. Please provide approval letter or letter stating it does not need a planning application.
3. A site plan will be needed of the property showing where the proposed opening is for the building and distances from property lines.
4. Plan views of the building would also be required showing the opening and where mechanical equipment is that will be replaced.
5. Information on what equipment is there currently and what it's being replaced with will also be required (if new equipment is heavier load than existing engineering may be required).
6. Stamped drawing did not upload correctly, please re-upload
|
Intake Approval | | | 3/11/2020 | | FAIL |
Jenny Nelson
|
|
|
no new information provided
|
Intake Approval | | | 3/6/2020 | | FAIL |
Jenny Nelson
|
|
|
Need completed submittal checklist
|
Application received | | | 2/28/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 28 2020 11:56AM
|