BLD-Energy code compliance | 7/15/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 7/15/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Framing/Rough-in | 7/13/2020 | 7/13/2020 | 7/13/2020 | P | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick missing bolt for hold down// g-4 missing 4.4 sds screws for face mount hangers.//20 door assemply garage side fire spk acess.
|
BLD-Other | 7/9/2020 | 7/9/2020 | 7/9/2020 | A | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 6/17/2020 | 6/18/2020 | 6/18/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Foundation | 4/27/2020 | 4/28/2020 | 4/28/2020 | P | PASS |
Brandon Shaw
|
|
|
Worn in progress...
|
BLD-Footing | 4/26/2020 | 4/27/2020 | 4/27/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 4/27/2020 | 4/27/2020 | 4/27/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 3/18/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/18/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/12/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 3/3/2020 | 3/3/2020 | 3/12/2020 | | DONE |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2020 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 3/12/2020 | | DONE |
|
|
|
ALL MET
|
Routing PW Grading-Hillside | 3/4/2020 | | 3/10/2020 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - FIRE | 3/3/2020 | 3/3/2020 | 3/5/2020 | | PASS |
Lee G Meredith
|
|
|
New SFH
Sprinklers are being provided, as noted on the A0.1 - Site Plan drawing. No fire review comments are being provided.
|
Routing - PLAN CHECK | 3/3/2020 | | 3/5/2020 | | PASS |
Debbie Sanine
|
|
|
|
Routing - MECHANICAL | 3/3/2020 | | 3/5/2020 | | PASS |
Chad Schwendiman
|
|
|
|
1st review completed | | | 3/5/2020 | | DONE |
Debbie Sanine
|
|
|
|
Route to Impact Fee Review | 3/3/2020 | 3/6/2020 | 3/4/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 3/3/2020 | | 3/4/2020 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/3/2020 | | 3/4/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/3/2020 | | 3/4/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 3/3/2020 | | 3/4/2020 | | PASS |
Michael Zawacki
|
|
|
Harris north, no site prep needed
|
Plans ACCEPTED BY PLAN TECH | | | 3/3/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/3/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/3/2020 | | PASS |
|
|
|
|
Application received | | | 3/2/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 2 2020 8:57AM
|