BLD-Footing | 8/7/2020 | 8/11/2020 | 8/11/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 7/27/2020 | 7/27/2020 | 7/27/2020 | | DONE |
Jason C. Taylor
|
|
|
**RETAINING WALLS**A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
(F) Reprint permit | | | 3/27/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/26/2020 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 3/17/2020 | 3/17/2020 | 3/26/2020 | | PASS |
Josh Bogle
|
|
|
03/23 retaining walls, ePlan - 1st done
|
Issue PAID IN FULL permit | | | 3/26/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/26/2020 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 3/26/2020 | | |
|
|
|
accepted resubmittal - called Craig, left message with questions/concerns
|
Routing - PLAN CHECK | 3/26/2020 | | 3/26/2020 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 3/26/2020 | | DONE |
|
|
|
MET
|
Routing PW Grading-Hillside | 3/17/2020 | | 3/24/2020 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
1st review completed | | | 3/24/2020 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/17/2020 | | 3/24/2020 | | FAIL |
Josh Bogle
|
|
|
discrepancies between docs about footing sizes
|
Routing - PLANNING | 3/17/2020 | | 3/18/2020 | | PASS |
Ethan Mansfield
|
|
|
JAB signed off for EOM working remotely (see e-mail)
|
Routing - PUBLIC WORKS | 3/17/2020 | | 3/17/2020 | | PASS |
Rita DeYoung
|
|
|
routed to hillside
|
Routing - Erosion and Sediment | 3/17/2020 | | 3/17/2020 | | PASS |
Andy J. Long
|
|
|
ESC site plan approved. Certified RP listed.
|
Plans ACCEPTED BY PLAN TECH | | | 3/17/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/17/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/17/2020 | | PASS |
|
|
|
|
Telephone call | | | 3/9/2020 | | DONE |
|
|
|
applicant asked about status - in appeals period until 3/13/20
|
Intake Approval | | | 3/3/2020 | | FAIL |
|
|
|
1.Please rotate all the drawings sheets so they are landscape.
2. please provide on the site plan where the retaining walls will be located at.
|
Application received | | | 3/2/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 2 2020 8:41PM
|