BLD-Energy code compliance | 6/5/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Other | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PASS |
Brandon Shaw
|
|
|
Soffit Inspection Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 6/1/2020 | 6/2/2020 | 6/2/2020 | A | FAIL |
Brandon Shaw
|
|
|
Provide Engineering approval for 2 1/2" hole bored thru 3 ply, bottom cord, trusses... See plans - red circles- for columns/bearing points. Need Mec...
|
BLD-Wall Bracing | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Foundation | 4/8/2020 | 4/9/2020 | 4/9/2020 | P | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 4/7/2020 | 4/8/2020 | 4/8/2020 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 4/6/2020 | 4/7/2020 | 4/7/2020 | P | NR |
Mike Jordan
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
PubWorks Subgrade Approval | 4/6/2020 | 4/6/2020 | 4/6/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 3/18/2020 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/18/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/18/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/18/2020 | | DONE |
|
|
|
met
|
Plan assigned to (D_S) Debbie | 3/16/2020 | 3/16/2020 | 3/17/2020 | | DONE |
Debbie Sanine
|
|
|
|
1st review completed | | | 3/17/2020 | | DONE |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/17/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 3/4/2020 | | 3/17/2020 | | PASS |
Rob Patrick
|
|
|
|
Plan assigned to (RDP) | 3/4/2020 | 3/4/2020 | 3/16/2020 | | DEFR |
Rob Patrick
|
|
|
03/23 sfd L2 ePlan
|
Routing PW Grading-Hillside | 3/4/2020 | | 3/9/2020 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Route to Impact Fee Review | 3/4/2020 | 3/7/2020 | 3/5/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 3/4/2020 | 3/4/2020 | 3/5/2020 | | PASS |
Lee G Meredith
|
|
|
New SFH
All measurements are within acceptable limits. Fire sprinklers are not required. No review comments provided.
|
Routing - MECHANICAL | 3/4/2020 | | 3/5/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 3/4/2020 | | 3/5/2020 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 3/4/2020 | | 3/4/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/4/2020 | | 3/4/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 3/4/2020 | | 3/4/2020 | | PASS |
Michael Zawacki
|
|
|
Harris north, no site prep needed
|
Plans ACCEPTED BY PLAN TECH | | | 3/4/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/4/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/4/2020 | | PASS |
|
|
|
|
Application received | | | 3/3/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 3 2020 7:21AM
|