BLD-Final | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | PASS |
Mike Jordan
|
|
|
Call for Access Phone #: ###-#### Inspection requested via web by Allen Jones
|
DOC - Permit Finaled | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | PASS |
Mike Jordan
|
|
|
All issues resolved.
|
BLD-Final | 7/6/2020 | 7/7/2020 | 7/7/2020 | P | NR |
Mike Jordan
|
|
|
Call for Access Phone #: ###-#### Inspection requested via web by Allen Jones. Needs mech. final.
|
BLD-Final | 7/3/2020 | 7/6/2020 | 7/6/2020 | A | FAIL |
Mike Jordan
|
|
|
call for access Phone #: ###-#### Inspection requested via web by Allen Jones. Complete install of smoke seal on 20min. door. Needs mech. final.
|
BLD-Energy code compliance | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Allen Jones
|
BLD-Framing/Rough-in | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Allen Jones
|
BLD-Framing/Rough-in | 4/30/2020 | 4/30/2020 | 4/30/2020 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Allen Jones. Nail off simpson hangars in garage. strapglue lam to 6x6. strap header to studs at mudroom. Strap double top plate cut at plumbing penetration in kithchen. Complete lateral bracing on A01, C01 and C02 trusses. Correction notice posted. Ok to insulate.
|
BLD-Framing/Rough-in | 4/6/2020 | 4/7/2020 | 4/7/2020 | A | PASS |
Mike Jordan
|
|
|
*Screened* - Zane Phone #: ###-####
|
BLD-Foundation | 3/20/2020 | 3/20/2020 | 3/20/2020 | P | PART |
Mike Jordan
|
|
|
wall // Allen Phone #: ###-####
|
OVERRIDE | | | 3/20/2020 | | |
|
|
|
|
OVERRIDE | | | 3/20/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 3/20/2020 | | DONE |
|
|
|
DO NOT ISSUE -plan mod
|
Plan Reviewer's activity | | | 3/20/2020 | | DONE |
Debbie Sanine
|
|
|
No residential plan mod review fee
|
Permit Ready to Issue | | | 3/20/2020 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/20/2020 | | DONE |
|
|
|
|
BLD-Footing | 3/19/2020 | 3/19/2020 | 3/19/2020 | P | PART |
Mike Jordan
|
|
|
As late as possible Phone #: 2084507023 >> Inspection requested via mobile web by Dion
|
Plan assigned to (D_S) Debbie | 3/19/2020 | 3/19/2020 | 3/19/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLANNING | 3/19/2020 | | 3/19/2020 | | PASS |
Sue Cummings
|
|
|
|
Routing - PLAN CHECK | 3/19/2020 | | 3/19/2020 | | PASS |
Debbie Sanine
|
|
|
|
Plan Modification Accepted | | | 3/19/2020 | | DONE |
|
|
|
Allen Jones from Hayden Homes emailed requesting a plan mod for patio engineering.
|
OVERRIDE | | | 3/9/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 3/3/2020 | 3/3/2020 | 3/9/2020 | | DONE |
Debbie Sanine
|
|
|
|
Issue PAID IN FULL permit | | | 3/9/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/9/2020 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 3/9/2020 | | 3/9/2020 | | PASS |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 3/9/2020 | | DONE |
|
|
|
MET
|
Routing - MECHANICAL | 3/3/2020 | | 3/5/2020 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 3/5/2020 | | FAIL |
Debbie Sanine
|
|
|
|
Route to Impact Fee Review | 3/3/2020 | 3/6/2020 | 3/4/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 3/3/2020 | | 3/4/2020 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/3/2020 | | 3/4/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/3/2020 | | 3/4/2020 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 3/3/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 3 2020 9:14AM
|
Intake Approval | | | 3/3/2020 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/3/2020 | | | | FAIL |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 3/19/2020 | | | | |
Debbie Sanine
|
|
|
|