Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD20-00769
StatusFinaled
Name C&C LLC
Site Address 11600 W FAIRVIEW AVE
Project NameIdaho Fitness Factory TI
Customer Number 
ePlanReviewYes
Description
(IDAHO FITNESS FACTORY TI) Permit for exterior remodel to existing 5,281 assembly fitness center. Approval is contingent upon adhering to the approved plans on file. Work to include: Removing existing exterior overhead door at back of tenant space infilling and replacing with exterior door from storage room; infill existing exterior door for storage room, and interior finished in compliance with Ch. 8 of the 2015 IBC. This building is fully fire sprinklered for area increase and story increase. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JJN**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/23/20207/24/20207/24/2020APASS
DetailsDave Hannah
Screened- Cory Phone #: ###-####
DOC - Permit Finaled7/24/20207/24/20207/24/2020PPASS
DetailsDave Hannah
FIRE-Final Inspection7/21/20207/22/20207/22/2020APASS
DetailsTroy Cobbley
life safety passed.


cory Phone #: ###-####
BLD-Final7/21/20207/21/20207/21/2020PNR
DetailsTell Riley
SCREENED // Cory Phone #: ###-####//need fire life safety and electrical finals prior to final building inspection//
BLD-Framing/Rough-in4/9/20204/10/20204/10/2020APASS
DetailsMike Jordan
screened // Cory Phone #: ###-####
Inspection Record Card- Bld  3/30/2020 DONE
Issue PAID IN FULL permit  3/27/2020 DONE
Telephone call  3/26/2020 DONE
SPOKE WITH CHRIS (PARCEL OWNER/GC) INFORMING HE NEEDS TO TURN IN 302 & 306
Route to Impact Fee Review3/23/20203/26/20203/24/2020 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Permit Ready to Issue  3/24/2020 DONE
All Met
Need GC
Need Revised Values
Plan assigned to (J_N)3/18/20203/18/20203/23/2020 DONE
DetailsJenny Nelson
03/23 L1 Idaho Fitness Factory ePlan
Routing - PLAN CHECK3/18/2020 3/23/2020 PASS
DetailsJenny Nelson
1st review completed  3/23/2020 DONE
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  3/23/2020 DONE
DetailsJenny Nelson
Routing - Design Review3/18/2020 3/19/2020 PASS
DetailsMichaella Owens
Intake Approval  3/17/2020 PASS
DetailsJavier Guzman
Intake Approval  3/5/2020 FAIL
DetailsBrian McGowan
Please provide or address the following for your prescreen to be approved:
1. A Key Plan was not provided.
2. No wall schedule or section was provided (sheathing, stud spacing, insulation, p.t. wood locations, etc.).
3. The door schedule specifies Type "A" and Material "E" but no schedule for what those are.
4. Do the red triangles indicate fire extinguisher locations?
Application received  3/3/2020 DONE
Application submitted via PDS Online on Mar 3 2020 2:40PM