First Notice | | 8/7/2020 | 8/10/2020 | | DONE |
|
|
|
mailed 7-14-2020
|
Permanent Occupancy | | | 7/28/2020 | | DONE |
|
|
|
|
BLD-Final | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Amar. Ok for perm occ.
|
FIRE-Final Inspection | 7/24/2020 | 7/24/2020 | 7/24/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. SCREENED // Pat Phone #: ###-####
|
Zoning Approval | 7/24/2020 | 7/24/2020 | 7/24/2020 | | DONE |
Michaella Owens
|
|
|
|
BLD-Energy code compliance | 6/4/2020 | 6/5/2020 | 6/5/2020 | A | PASS |
Mike Jordan
|
|
|
Pat *screened* Phone #: ###-####plan mod and engineering recived.
|
BLD-Framing/Rough-in | 6/4/2020 | 6/5/2020 | 6/5/2020 | A | PASS |
Mike Jordan
|
|
|
Pat *screened* Phone #: ###-####
|
BLD-Framing/Rough-in | 6/1/2020 | 6/2/2020 | 6/2/2020 | A | PART |
Mike Jordan
|
|
|
Matt - Call ahead for access *Screened* Phone #: ###-####. Needs to provide resubmittal to show actual construction of walls in the field.
|
BLD-Framing/Rough-in | 5/21/2020 | 5/22/2020 | 5/22/2020 | A | CANC |
Mike Jordan
|
|
|
Screened- Pat Phone #: ###-####
|
Print Occupancy Form | | | 4/20/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/20/2020 | | DONE |
|
|
|
|
Plan assigned to (JG) | 3/24/2020 | 3/24/2020 | 4/16/2020 | | PASS |
Javier Guzman
|
|
|
04/13 L3 Buildtmore Co. ePlan
|
Routing - PLAN CHECK | 3/24/2020 | | 4/16/2020 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 4/16/2020 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/16/2020 | | DONE |
|
|
|
MET GC FORM
MET REVISED VALUE
met
achd
|
Routing - FIRE | 3/24/2020 | 3/24/2020 | 4/14/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
Routing PW Environmental | 3/26/2020 | | 4/10/2020 | | PASS |
Zach Conde
|
|
|
PER ZACH: Converting two bays of a car wash into office space, leaving two East side bays as car wash. Approved on ePlan with this comment: "Approved with existing oil/sediment interceptor for remaining two car wash bays." Please pass on Tidemark.
|
Routing PW Solid Waste | 3/26/2020 | | 3/31/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PUBLIC WORKS | 3/24/2020 | | 3/26/2020 | | PASS |
Morgan Webb
|
|
|
WASH BAYS ARE STAYING AND WERE PREVIOUSLY PAID FOR.
|
Routing - PLUMBING | 3/24/2020 | | 3/25/2020 | | PASS |
Dan Ediger
|
|
|
per plans and ISPC
|
Routing - PLANNING | 3/24/2020 | | 3/24/2020 | | PASS |
Karla Nelson
|
|
|
|
Routing - Addressing | 3/24/2020 | | 3/24/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 3/24/2020 | | 3/24/2020 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 3/24/2020 | | 3/24/2020 | | PASS |
Michaella Owens
|
|
|
|
Routing - Erosion and Sediment | 3/24/2020 | | 3/24/2020 | | PASS |
Michael Zawacki
|
|
|
|
Intake Approval | | | 3/17/2020 | | PASS |
|
|
|
|
Intake Approval | | | 3/5/2020 | | FAIL |
Jenny Nelson
|
|
|
Need fire flow letter
|
Application received | | | 3/4/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 4 2020 8:49AM
|
Second Notice | | 8/20/2020 | | | |
|
|
|
|