BLD-Final | 5/20/2020 | 5/21/2020 | 5/21/2020 | A | PASS |
Dave Hannah
|
|
|
Greg *screened* Phone #: ###-####
|
FIRE-Final Inspection | 5/20/2020 | 5/20/2020 | 5/20/2020 | P | PASS |
Jim Page
|
|
|
Generator power transfer was witnessed and verified by a city of boise employee, final life fire safety inspection for scope of work is complete.
Greg Phone #: ###-####
|
BLD-Final | 5/11/2020 | 5/12/2020 | 5/12/2020 | A | PEND |
Dave Hannah
|
|
|
Please call for access, requests after 9 - Greg Phone #: ###-####
|
(F) Reprint permit | | | 3/31/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/31/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/30/2020 | | DONE |
|
|
|
|
Plan assigned to (JG) | 3/5/2020 | 3/5/2020 | 3/25/2020 | | PASS |
Javier Guzman
|
|
|
03/18 L2 Generator Replacement Paper Plans
|
Routing - PLAN CHECK | 3/5/2020 | | 3/25/2020 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 3/25/2020 | | DONE |
Javier Guzman
|
|
|
|
1st review completed | | | 3/25/2020 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/25/2020 | | DONE |
|
|
|
|
Routing - FIRE | 3/6/2020 | 3/5/2020 | 3/24/2020 | | PASS |
Joe Bruce
|
|
|
Printed out case summary and attached to plans. Added notes for PDS Fire Inspector on the plans.
|
Routing - Addressing | 3/6/2020 | | 3/6/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/5/2020 | | 3/6/2020 | | PASS |
Candy A. Nichols
|
|
|
NO NEW PLUMBING
|
Intake Approval | | | 3/5/2020 | | PASS |
|
|
|
|
Application received | | 3/5/2020 | | | |
|
|
|
|
Routing - Design Review | 3/25/2020 | | | | PASS |
Katelyn Menuge
|
|
|
Paint pipe to blend with tones of adajcent wall.
|