BLD-Final | 8/12/2020 | 8/13/2020 | 8/13/2020 | P | PART |
Dave Hannah
|
|
|
Curtis *screened* Phone #: ###-#### ok for tco phase one everything south of 3hr firewall
|
FIRE-Final Inspection | 8/6/2020 | 8/13/2020 | 8/13/2020 | A | PART |
Jim Page
|
|
|
Fire sprinkler inspection for TCO phase 1 complete, fire alarm for phase 1 TCO complete, fire extinguishers for TCO phase 1 area are placed with current inspection tags. Push button for access controlled doors to be raised between 40 to 48 inches as discussed. Three exit signs to be added and 2 too be relocated as discussed. Will verify noted items on final life fire safety phase 2 inspection. Life fire safety for TCO phase 1 is complete, signatures provided on permit sign off card for TCO phase 1.
Curt *screened* Phone #: ###-####
|
FIRE-Alarm Testing | 8/12/2020 | 8/13/2020 | 8/12/2020 | A | CANC |
Jim Page
|
|
|
Fire alarm inspection has been requested under the fire alarm FIR permit, this request is cancelled.
Screened- Curtis Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/10/2020 | 8/10/2020 | 8/10/2020 | P | PART |
Dave Hannah
|
|
|
Curtis *screened Phone #: ###-#### ok to cut in perimator
|
BLD-Ceiling Grid Inspection | 8/6/2020 | 8/6/2020 | 8/7/2020 | P | PART |
Dave Hannah
|
|
|
Curt *screened* Phone #: ###-#### nw corner ok
|
FIRE-Conference | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | DONE |
Jim Page
|
|
|
Fire conference is complete.
Curtis *screened* Phone #: ###-####
|
FIRE-Conference | 7/31/2020 | 8/3/2020 | 8/3/2020 | A | CANC |
Jim Page
|
|
|
Was scheduled for 04AUG2020, this request is cancelled.
Curtis *screened* Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/30/2020 | 7/31/2020 | 8/1/2020 | P | PART |
Dave Hannah
|
|
|
Screened- Curtis Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/24/2020 | 7/27/2020 | 7/24/2020 | A | PART |
Dave Hannah
|
|
|
SCREENED // Curtis Phone #: ###-#### ok to cut in bourders
|
BLD-Ceiling Grid Inspection | 7/21/2020 | 7/21/2020 | 7/21/2020 | P | PART |
Brandon Shaw
|
|
|
*screened* Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | PART |
Mike Jordan
|
|
|
Curtis - /*Screened*/ Phone #: ###-####. Luncroom and last meeting room ok pending fire and mech. Ok for borders.
|
BLD-Framing/Rough-in | 6/24/2020 | 6/24/2020 | 6/24/2020 | P | PART |
Dave Hannah
|
|
|
screened // Curtis Phone #: ###-#### fire caulking on 2hr wall ok
|
BLD-Ceiling Grid Inspection | 6/16/2020 | 6/16/2020 | 6/17/2020 | P | PART |
Dave Hannah
|
|
|
screened // Curtis Phone #: ###-#### parts of south end ok to flood
|
BLD-Ceiling Grid Inspection | 6/10/2020 | 6/11/2020 | 6/11/2020 | A | PART |
Dave Hannah
|
|
|
Curtis Phone #: ###-#### ok to cut in bourders
|
BLD-Ceiling Grid Inspection | 6/9/2020 | 6/10/2020 | 6/10/2020 | A | PART |
Dave Hannah
|
|
|
Screened- Curtis Phone #: ###-#### ok to cut in bourders after elec oks
|
BLD-Framing/Rough-in | 5/27/2020 | 5/27/2020 | 5/27/2020 | P | PASS |
Jim Storey
|
|
|
Curtis Phone #: ###-#### ceilling and walls ok center restarooms// north partions of 4 hr wall ok to cover.
|
BLD-Framing/Rough-in | 5/11/2020 | 5/12/2020 | 5/12/2020 | A | PART |
Dave Hannah
|
|
|
Curtis *screened* Phone #: ###-#### sw corner ok to cover
|
BLD-Framing/Rough-in | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Jim Storey
|
|
|
Curtis Phone #: ###-#### interior walls ok to cover only
|
Print Occupancy Form | | | 5/1/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/29/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/29/2020 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 3/12/2020 | 3/12/2020 | 4/22/2020 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 2nd Comp - L3 Tandem Diabetes Care
|
Routing - PLAN CHECK | 4/22/2020 | | 4/22/2020 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/22/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/22/2020 | | DONE |
|
|
|
MET Revised Value
MET GC
doc final early start BLD20-00978
|
Routing - PLAN CHECK | 4/20/2020 | | 4/21/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Flood Plain | 4/20/2020 | | 4/21/2020 | | PASS |
Jason C. Taylor
|
|
|
(Market Value submitted) Project does not meet the Substantial Improvements section of Boise Floodplain Ordinance .No floodplain requirements. If you have any questions, please call Jason Taylor at ###-####.
|
Routing - Design Review | 4/20/2020 | | 4/21/2020 | | PASS |
KayCee Babb
|
|
|
No additional screening required, per Design Review response letter.
|
Routing - PLUMBING | 4/20/2020 | | 4/21/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC
|
Routing - MECHANICAL | 4/20/2020 | | 4/20/2020 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/13/2020 | 4/16/2020 | 4/13/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/12/2020 | | 4/13/2020 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 4/13/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 3/12/2020 | 3/12/2020 | 4/6/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case.
|
Routing - MECHANICAL | 3/12/2020 | | 3/16/2020 | | PASS |
Troy James
|
|
|
|
Routing PW Solid Waste | 3/12/2020 | | 3/16/2020 | | PASS |
Evan Carpenter
|
|
|
Existing enclosures.
|
Routing PW Flood Plain | 3/12/2020 | | 3/13/2020 | | FAIL |
Jason C. Taylor
|
|
|
A portion of the subject property is within the regulatory floodplain. This project must comply with the Boise Floodplain Ordinance (B.C.C. 11-08). Building must be assessed for substantial improvements based on current market value. Please submit a market value assessment from a licensed broker or agent. Alternatively, an Elevation Certificate may be uploaded to show the structure is elevated above the most current base flood elevation (contact Public Works Floodplain Coordinator for map) in the area. If you have any questions, please call Jason Taylor at ###-####.
|
Routing PW Environmental | 3/12/2020 | | 3/13/2020 | | PASS |
Zach Conde
|
|
|
|
Routing - PLANNING | 3/12/2020 | | 3/13/2020 | | PASS |
Karla Nelson
|
|
|
Office is an allowed use, exterior changes may require Design Review.
|
Routing - Addressing | 3/12/2020 | | 3/12/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/12/2020 | | 3/12/2020 | | PASS |
Candy A. Nichols
|
|
|
CREDIT FOR DEMO
|
Routing - Erosion and Sediment | 3/12/2020 | | 3/12/2020 | | PASS |
Michael Zawacki
|
|
|
TI ESC not needed
|
Routing - Design Review | 3/12/2020 | | 3/12/2020 | | FAIL |
KayCee Babb
|
|
|
Heights of new RTU and existing parapet needs to be provided to Design Review Staff. If parapets are shorter than proposed units, separate screening will be required.
|
Routing - PLUMBING | 3/12/2020 | | 3/12/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 3/11/2020 | | PASS |
|
|
|
|
Intake Approval | | | 3/9/2020 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Remove statement “NOT FOR CONSTRUCTION” from plan sheet T0.1
• Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on plan sheet S1.0, S1.1, S1.2, S2.1, S2.2 see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
|
Application received | | | 3/5/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 5 2020 1:58PM
|