BLD-Final | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PASS |
Brandon Shaw
|
|
|
|
DOC - Permit Finaled | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 7/15/2020 | 7/16/2020 | 7/16/2020 | A | NR |
Brandon Shaw
|
|
|
R314.2.2 Smake alarms...
|
BLD-Framing/Rough-in | 5/22/2020 | 5/26/2020 | 5/26/2020 | A | PASS |
Brandon Shaw
|
|
|
call for access and ahead Steve Phone #: ###-####
|
Place hold on job | 5/4/2020 | | 5/22/2020 | | DONE |
Gabe Brenner
|
|
|
GC needs to email signed permit- sent a second email
|
Issue PAID IN FULL permit | | | 4/28/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/28/2020 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 3/25/2020 | 3/25/2020 | 4/17/2020 | | PASS |
Josh Bogle
|
|
|
03/30 remodel, ePlan - 1st done
|
Routing - PLAN CHECK | 4/17/2020 | | 4/17/2020 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2020 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 4/17/2020 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 4/14/2020 | | 4/14/2020 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan
|
Routing - PLAN CHECK | 4/14/2020 | | 4/14/2020 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan, called Eric
|
1st review completed | | | 3/31/2020 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/25/2020 | | 3/31/2020 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan
|
Routing - PLANNING | 3/25/2020 | | 3/25/2020 | | PASS |
Crystal Rain
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/25/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/25/2020 | | DONE |
|
|
|
no intake fee taken
|
Application received | | | 3/6/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 6 2020 8:58AM
|