First Notice | 7/23/2020 | 7/23/2020 | 8/11/2020 | | DONE |
Brandon Shaw
|
|
|
MAILED 8-14-2020
|
BLD-Final | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Allen Nunnally
|
DOC - Permit Finaled | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 7/21/2020 | 7/22/2020 | 7/22/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-#### Inspection requested via web by Allen Nunnally
|
FIRE-Final Inspection | 6/30/2020 | 7/1/2020 | 7/1/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need current inspection for fire extinguisher, remove thumbturn dead bolt on west side door and provide sticker. Inspection performed by Greg
Phone #: ###-#### Inspection requested via web by Allen Nunnally
|
BLD-Final | 6/30/2020 | 6/30/2020 | 6/30/2020 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Allen Nunnally. Needs fire final. Called Allen and left message.
|
BLD-Ceiling Grid Inspection | 6/1/2020 | 6/2/2020 | 6/2/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Allen Nunnally
|
BLD-Framing/Rough-in | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | PASS |
Mike Jordan
|
|
|
Inspection requested via web by rick pew. Interior steel stud framed walls and hardlid in bathroom. Noted to contractor that a mech. permit not yet pulled, flex for vent fan in bathroom needs inspected prior to cover.
|
Route to Impact Fee Review | 3/31/2020 | 4/3/2020 | 4/1/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Issue PAID IN FULL permit | | | 4/1/2020 | | DONE |
|
|
|
email permit and inspection card to- will@strothgeneral.com
|
Inspection Record Card- Bld | | | 4/1/2020 | | DONE |
|
|
|
|
Telephone call | | | 4/1/2020 | | DONE |
|
|
|
eplan will need to be release
|
Plan assigned to (M_H) | 3/19/2020 | | 3/31/2020 | | DONE |
Michael Hanson
|
|
|
03/24 #518 L1 ePlan - Enterprise Car Rental
|
Routing - PLAN CHECK | 3/19/2020 | | 3/31/2020 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 3/31/2020 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/31/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 3/31/2020 | | DONE |
|
|
|
ALL MET
NEED
GC
REV VALUE
|
Routing - PUBLIC WORKS | 3/19/2020 | | 3/20/2020 | | PASS |
Rita DeYoung
|
|
|
Credit for demo no new fees per Morgan
|
Routing - Addressing | 3/19/2020 | | 3/19/2020 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 3/18/2020 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 3/10/2020 | | FAIL |
Brian McGowan
|
|
|
Please address or provide the following for your Prescreen to be approved;
1. The Application needs to be uploaded.
2. Planning andf Zoning letters of approval for exterior modifications.
3. Door hardware to be specified on the plans per door. "All to match building standards" is not acceptable.
4. Sheet a2.31 is labeled a2.21 in the drawing folder. Just an (FYI)
5. The existing rooms and restrooms in the Public Lobby and Offices should be shown on a Key Plan. Egress from the entire building needs to be evaluated with the alterations. The plumbing fixture requirements for occupancy should be evaluated for compliance and noted on the plans.
6. It appears the new office area was storage or garage previously. A change of use requires the lighting and mechanical to be reevaluated for the new occupancy/use. Provide mechanical and electrical calculations and plans as required for a change of use in these areas OR letters (emails) from the Chief Electrical and Chief Mechanical Inspectors verifying no calculations and/or plans are required.
|
Application received | | | 3/6/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 6 2020 11:49AM
|
Second Notice | | 8/21/2020 | | | |
|
|
|
|