BLD-Foundation | 5/6/2020 | 5/7/2020 | 5/7/2020 | P | PASS |
Tony Young
|
|
|
rebar pool // ryan Phone #: ###-####
|
PubWorks Subgrade Approval | 5/1/2020 | 5/1/2020 | 5/1/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable has been received by Public Works. concrete inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 3/23/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/20/2020 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 3/10/2020 | 3/10/2020 | 3/20/2020 | | PASS |
Josh Bogle
|
|
|
03/16 pool, paper - 1st done
|
Meeting | | | 3/20/2020 | | DONE |
|
|
|
emailed ryan informing the fees, how to pay and we will put plans in the mail
|
Inspection Record Card- Bld | | | 3/20/2020 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 3/20/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 3/20/2020 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 3/19/2020 | | 3/19/2020 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. Please allow 24 hours for subgrade approval processing. If you have any questions call Melissa Jannusch ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
1st review completed | | | 3/16/2020 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/10/2020 | | 3/16/2020 | | PASS |
Josh Bogle
|
|
|
Plan Review pass pending Hillside approval
|
Routing PW Grading-Hillside | 3/10/2020 | | 3/13/2020 | | FAIL |
Melissa Jannusch
|
|
|
See email to aplicant
|
Routing - Erosion and Sediment | 3/10/2020 | | 3/13/2020 | | PASS |
Andy J. Long
|
|
|
ESCP waiver request approved. RP listed.
**Please schedule ESC Site preparation at time of permit issue. Project is next to surface water**
|
Routing PW Flood Plain | 3/10/2020 | | 3/11/2020 | | PASS |
Jason C. Taylor
|
|
|
Project is outside Special Flood Hazard Area, no floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Routing Walk-In (Zoning) | 3/10/2020 | 3/10/2020 | 3/10/2020 | A | PASS |
Kevin Holmes
|
|
|
|
Routing Walk-In (BLD) | 3/10/2020 | 3/10/2020 | 3/10/2020 | A | PASS |
Josh Bogle
|
|
|
took in for level two review
|
Application received | | 3/10/2020 | | | |
|
|
|
|
Routing - PUBLIC WORKS | 3/13/2020 | | | | FAIL |
Morgan Webb
|
|
|
SEE HILLSIDE FOR FAIL
|