BLD-Wall Bracing | 8/10/2020 | 8/11/2020 | 8/11/2020 | A | PASS |
Tony Young
|
|
|
Is it OK to have an attic access above a stacked washer/dryer? Phone #: ###-#### Inspection requested via web by David Wipper// yes and exterior ok to cover
|
BLD-Foundation | 7/24/2020 | 7/27/2020 | 7/27/2020 | A | PASS |
Tony Young
|
|
|
screened // CHarlie Phone #: ###-####
|
BLD-Footing | 7/24/2020 | 7/24/2020 | 7/24/2020 | P | PART |
Tony Young
|
|
|
screened // CHarlie Phone #: ###-####// small rear planter/ retaining wall footing
|
BLD-Foundation | 6/22/2020 | 6/22/2020 | 6/22/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 6/19/2020 | 6/22/2020 | 6/22/2020 | A | NR |
Dave Hannah
|
|
|
Victor Phone #: ###-####
|
BLD-Footing | 6/16/2020 | 6/16/2020 | 6/16/2020 | P | PASS |
Tony Young
|
|
|
Victory *Screened* Phone #: ###-####
|
BLD-Footing | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | NR |
Tony Young
|
|
|
Victory *Screened* Phone #: ###-####// needs soils approval 1st
|
PubWorks Subgrade Approval | 6/16/2020 | 6/16/2020 | 6/16/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 6/3/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/3/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 4/3/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 3/17/2020 | 3/17/2020 | 4/3/2020 | | DONE |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2020 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 4/3/2020 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 4/1/2020 | | 4/1/2020 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing PW Grading-Hillside | 3/17/2020 | | 3/25/2020 | | FAIL |
Melissa Jannusch
|
|
|
see changemarks in ePlan.
|
1st review completed | | | 3/23/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 3/17/2020 | | 3/23/2020 | | PASS |
Debbie Sanine
|
|
|
|
Routing - PUBLIC WORKS | 3/17/2020 | | 3/20/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - FIRE | 3/17/2020 | 3/17/2020 | 3/19/2020 | | PASS |
Lee G Meredith
|
|
|
New SFH
Sprinklers are not required. All measurements are within acceptable limits.
|
Route to Impact Fee Review | 3/17/2020 | 3/20/2020 | 3/18/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 3/17/2020 | | 3/18/2020 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 3/17/2020 | | 3/18/2020 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Addressing | 3/17/2020 | | 3/17/2020 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/17/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/17/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/17/2020 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/17/2020 | | 3/17/2020 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Need to provide current certified Responsible Person for project. Site preparation inspection is required.
|
Intake Approval | | | 3/11/2020 | | FAIL |
|
|
|
NEED
Stair section detail
Show Crawlspace access
|
Application received | | | 3/10/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 10 2020 1:18PM
|