Permit Information
Permit NumberBLD20-00880
StatusIssued
Name RENAISSANCE REMODELING
Site Address 4906 N QUAIL SUMMIT PL
Project NamePatio Cover
Customer Number 
ePlanReviewYes
Description
HILLSIDE - WUI - SPECIAL INSPECTIONS - Permit to build a 272sq' patio cover. All work per plans, notations, attachments, engineering, local codes & ordinances. **JAB** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Framing/Rough-in6/17/20206/17/20206/17/2020PPASS
DetailsTony Young
Kent *screened* Phone #: ###-####
BLD-Footing6/3/20206/4/20206/4/2020APASS
DetailsTony Young
screened - rebar - Kent Phone #: ###-####
PubWorks Subgrade Approval6/4/20206/4/20206/4/2020 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Issue PAID IN FULL permit  4/23/2020 DONE
Plan assigned to (JAB) Josh4/9/20204/9/20204/17/2020 PASS
DetailsJosh Bogle
04/15 patio cover, ePlan - 1st done
Routing - PLAN CHECK4/17/2020 4/17/2020 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  4/17/2020 DONE
DetailsJosh Bogle
ESC no - Energy no
Permit Ready to Issue  4/17/2020 DONE
met
1st review completed  4/10/2020 FAIL
DetailsJosh Bogle
Routing - PLAN CHECK4/9/2020 4/10/2020 FAIL
DetailsJosh Bogle
see notes in ePlan
Routing - PLANNING4/9/2020 4/9/2020 PASS
DetailsSue Cummings
Routing - PUBLIC WORKS4/9/2020 4/9/2020 PASS
DetailsCandy A. Nichols
Routing PW Grading-Hillside4/9/2020 4/9/2020 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Plans ACCEPTED BY PLAN TECH  4/9/2020 DONE
Recd Pcfee & Taken To Pln CK  4/9/2020 DONE
Intake Approval  4/9/2020  
Intake Approval  4/8/2020 FAIL
2nd prescreen- Please upload the drawings from the engineer to drawings in a separate files. I went ahead and deleted the packet from documents.
Meeting  4/3/2020 DONE
CAT I hillside permit can be accepted for building permit review. MMJ// this note was on the Eplan from Melissa. FAIL our prescreen so i removed so the applicant will not get confused.
Intake Approval  4/3/2020 FAIL
1st Prescreen-
1. Plans need to be individual
2. Files names correctly.
3. Site plans was cut off, need one that shows the whole property lines.
4. Application needed- None was uploaded
Drawings were deleted
Routing Walk-In (Zoning)3/11/20203/11/20203/11/2020AFAIL
DetailsJeff Lowe
needs to run things through PW Hillside first.
Application received 3/11/2020