Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD20-00884
StatusIssued
Name SUPERIOR HOMES SOLUTIONS
Site Address 181 W HIGHLAND VIEW DR
Project NameJames & Kim Stuart Residence
Customer Number 
ePlanReviewYes
Description
***W.U.I. HILLSIDE LOT ZONE A; CLASS "A" ROOF AND NON-COMBUSTIBLE EXTERIOR MATERIALS REQUIRED****** Permit for the construction of a new 4568 sq. ft., two story (first story 3010 sq. ft., second story 1558sq. ft) single family dwelling with 4 bedrooms, 4.5 bathrooms, approximately 2302 sq. ft. of covered patio/porch and a 2177 sq. ft. attached garage per the approved plans and any notations. Prescriptive Energy Compliance. R-1B zoning and setbacks per planning. ***RDP ***Sprinklers are being provided, as noted on the site plan***LGM A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Foundation5/18/20205/19/20205/19/2020PPART
DetailsTony Young
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constr// 425 already looked at
BLD-Footing5/10/20205/11/20205/11/2020PPASS
DetailsDave Hannah
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
BLD-Footing5/8/20205/8/20205/8/2020PCANC
DetailsTony Young
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru Inspection cancelled via mobile web on Friday, May 08, 2020.
BLD-Footing5/7/20205/8/20205/8/2020ACANC
DetailsTony Young
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo Aggregate constru Inspection cancelled via mobile web on Friday, May 08, 2020.
PubWorks Subgrade Approval4/29/20204/29/20204/29/2020 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
Telephone call  4/13/2020 DONE
Emailed GC to inform them that not all the fees were paid. Once the remaining fees have been paid we can issue the permits.
Issue PAID IN FULL permit  4/13/2020 DONE
Inspection Record Card- Bld  4/13/2020 DONE
Permit Ready to Issue  4/10/2020 DONE
Plan assigned to (RDP)3/16/20203/16/20204/9/2020 DONE
DetailsRob Patrick
1st Review Complete 03/30 Failed: 04/02 sfd L2 ePlan
Routing - PLAN CHECK4/9/2020 4/9/2020 PASS
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  4/9/2020 DONE
DetailsRob Patrick
Routing PW Grading-Hillside4/7/2020 4/7/2020 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
1st review completed  3/31/2020 FAIL
DetailsRob Patrick
Routing - PLAN CHECK3/16/2020 3/31/2020 FAIL
DetailsRob Patrick
Corrections Req'd
Routing PW Grading-Hillside3/17/2020 3/30/2020 FAIL
DetailsMelissa Jannusch
see changemarks in ePlan
Routing - PLANNING3/16/2020 3/23/2020 PASS
DetailsDavid Moser
Route to Impact Fee Review3/16/20203/19/20203/17/2020 PASS
DetailsTravis P Black
Initial residential review of new SFD permits requested for now.
Routing - FIRE3/16/20203/16/20203/17/2020 PASS
DetailsLee G Meredith
Fire sprinklers are being provided, as noted on the Site Plan.
Routing - MECHANICAL3/16/2020 3/17/2020 PASS
DetailsTroy James
Routing - Addressing3/16/2020 3/17/2020 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS3/16/2020 3/17/2020 PASS
DetailsRita DeYoung
Routing - Erosion and Sediment3/16/2020 3/17/2020 PASS
DetailsAndy J. Long
VOID - see ESC20-00264. ESC permit issued with site grading and drainaige permit GRD20-00013
Plans ACCEPTED BY PLAN TECH  3/16/2020 DONE
Intake Approval  3/16/2020 PASS
Recd Pcfee & Taken To Pln CK  3/16/2020 DONE
Intake Approval  3/12/2020 FAIL
per hillside Prior to acceptance for building permit review please upload a copy of MTI's slope stability report. MMJ 3-12-2020
Application received  3/11/2020 DONE
Application submitted via PDS Online on Mar 11 2020 2:16PM
Routing - Erosion and Sediment3/11/2020 3/11/2020 PASS
DetailsAndy J. Long
VOID - see ESC20-00264. ESC permit issued with site grading and drainaige permit GRD20-00013