BLD-Foundation | 5/18/2020 | 5/19/2020 | 5/19/2020 | P | PART |
Tony Young
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constr// 425 already looked at
|
BLD-Footing | 5/10/2020 | 5/11/2020 | 5/11/2020 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 5/8/2020 | 5/8/2020 | 5/8/2020 | P | CANC |
Tony Young
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru Inspection cancelled via mobile web on Friday, May 08, 2020.
|
BLD-Footing | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | CANC |
Tony Young
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo Aggregate constru Inspection cancelled via mobile web on Friday, May 08, 2020.
|
PubWorks Subgrade Approval | 4/29/2020 | 4/29/2020 | 4/29/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Telephone call | | | 4/13/2020 | | DONE |
|
|
|
Emailed GC to inform them that not all the fees were paid. Once the remaining fees have been paid we can issue the permits.
|
Issue PAID IN FULL permit | | | 4/13/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/13/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/10/2020 | | DONE |
|
|
|
|
Plan assigned to (RDP) | 3/16/2020 | 3/16/2020 | 4/9/2020 | | DONE |
Rob Patrick
|
|
|
1st Review Complete 03/30 Failed: 04/02 sfd L2 ePlan
|
Routing - PLAN CHECK | 4/9/2020 | | 4/9/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2020 | | DONE |
Rob Patrick
|
|
|
|
Routing PW Grading-Hillside | 4/7/2020 | | 4/7/2020 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
1st review completed | | | 3/31/2020 | | FAIL |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 3/16/2020 | | 3/31/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing PW Grading-Hillside | 3/17/2020 | | 3/30/2020 | | FAIL |
Melissa Jannusch
|
|
|
see changemarks in ePlan
|
Routing - PLANNING | 3/16/2020 | | 3/23/2020 | | PASS |
David Moser
|
|
|
|
Route to Impact Fee Review | 3/16/2020 | 3/19/2020 | 3/17/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 3/16/2020 | 3/16/2020 | 3/17/2020 | | PASS |
Lee G Meredith
|
|
|
Fire sprinklers are being provided, as noted on the Site Plan.
|
Routing - MECHANICAL | 3/16/2020 | | 3/17/2020 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 3/16/2020 | | 3/17/2020 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/16/2020 | | 3/17/2020 | | PASS |
Rita DeYoung
|
|
|
|
Routing - Erosion and Sediment | 3/16/2020 | | 3/17/2020 | | PASS |
Andy J. Long
|
|
|
VOID - see ESC20-00264. ESC permit issued with site grading and drainaige permit GRD20-00013
|
Plans ACCEPTED BY PLAN TECH | | | 3/16/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/16/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/16/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/12/2020 | | FAIL |
|
|
|
per hillside Prior to acceptance for building permit review please upload a copy of MTI's slope stability report. MMJ 3-12-2020
|
Application received | | | 3/11/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 11 2020 2:16PM
|
Routing - Erosion and Sediment | 3/11/2020 | | 3/11/2020 | | PASS |
Andy J. Long
|
|
|
VOID - see ESC20-00264. ESC permit issued with site grading and drainaige permit GRD20-00013
|