Permit Information
Permit NumberBLD20-00888
StatusFinaled
Name BLUE RAVEN SOLAR LLC
Site Address 3810 W GREENBRIER DR
Project NameRobin Connick PV
Customer Number 
ePlanReviewYes
Description
Permit for 192sq' of roof-mounted, grid-tied Photo-voltaic panels with micro-inverters; panels in 2 arrays. No work needed to the existing roof structure per engineer’s roof evaluation. All racking, modules, and other listed equipment must be installed by a certified installer. All work per plans, engineering, manufacturer’s specs, & local code. Separate electrical permit required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/25/20203/26/20203/26/2020APASS
DetailsJim Storey
On Site Contact: Mierins Rozentals. ###-####
Please call ahead thank you! Phone #: ###-#### Inspection requested via web by BRS Permitting No work needed to the existing roof structure per engineer’s roof evaluation.
DOC - Permit Finaled3/26/20203/26/20203/26/2020PPASS
DetailsJim Storey
No work needed to the existing roof structure per engineer’s roof evaluation.
BLD-Framing/Rough-in3/23/20203/24/20203/24/2020APASS
DetailsJim Storey
Jay Walters (###-####) will be the on site contact Phone #: ###-#### Inspection requested via web by BRS Permitting No work needed to the existing roof structure per engineer’s roof evaluation
Issue PAID IN FULL permit  3/19/2020 DONE
Inspection Record Card- Bld  3/19/2020 DONE
Plan assigned to (JAB) Josh3/11/20203/11/20203/17/2020 PASS
DetailsJosh Bogle
03/17 PV, ePlan
Routing - PLAN CHECK3/11/2020 3/17/2020 PASS
DetailsJosh Bogle
1st review completed  3/17/2020 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  3/17/2020 DONE
DetailsJosh Bogle
ESC no - Energy no
Permit Ready to Issue  3/17/2020 DONE
MET
Routing - PLANNING3/11/2020 3/12/2020 PASS
DetailsSue Cummings
Application received  3/11/2020 DONE
Application submitted via PDS Online on Mar 11 2020 3:18PM
Plans ACCEPTED BY PLAN TECH  3/11/2020 DONE
Intake Approval  3/11/2020 PASS
Recd Pcfee & Taken To Pln CK  3/11/2020 DONE