Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD20-00893
StatusIssued
Name H2O POOLS & DESIGN LLC
Site Address 825 N TROUTNER WAY
Project NameKissler Pool
Customer Number 
ePlanReviewNo
Description
Permit for a 932sq’ swimming pool and 190sq' spa, shotcrete construction. Barrier requirements per 2015 ISPSC being satisfied with fence, gates, and alarms. All work per plans, engineering, & local code. Separate electrical & mechanical permits required. **JAB** A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. Please allow 24 hours for subgrade approval processing. If you have any questions call Melissa Jannusch 208-608-7168.

Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Footing4/16/20204/16/20204/16/2020PPASS
DetailsBrandon Shaw
Rebar inspection on swimming pool. Phone #: ###-#### Inspection requested via web by Mark Wright
BLD-Footing4/15/20204/16/20204/16/2020AFAIL
DetailsJim Storey
Rebar inspection on swimming pool Phone #: ###-#### Inspection requested via web by Mark Wright A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. Please allow 24 hours for subgrade approval processing. If you have any questions call Melissa Jannusch ###-####.
PubWorks Subgrade Approval4/16/20204/16/20204/16/2020 DONE
DetailsMelissa Jannusch
Pool House and pool bottom: A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. A footing inspection may now be scheduled with the Building Department.
Plan assigned to (JAB) Josh3/12/20203/12/20203/17/2020 PASS
DetailsJosh Bogle
03/18 pool, paper
Routing - PLAN CHECK3/12/2020 3/17/2020 PASS
DetailsJosh Bogle
1st review completed  3/17/2020 DONE
DetailsJosh Bogle
Inspection Record Card- Bld  3/17/2020 DONE
DetailsJosh Bogle
Case Summary (BLD)  3/17/2020 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  3/17/2020 DONE
DetailsJosh Bogle
ESC yes - Energy no
Permit Ready to Issue  3/17/2020 DONE
MET
Issue PAID IN FULL permit  3/17/2020 DONE
Routing Walk-In (BLD)3/16/20203/16/20203/16/2020APASS
DetailsJosh Bogle
bringing in additional information
Routing PW Grading-Hillside3/16/2020 3/16/2020 PASS
DetailsMelissa Jannusch
POOL ONLY
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. Please allow 24 hours for subgrade approval processing. If you have any questions call Melissa Jannusch ###-####.

Routing PW Grading-Hillside3/12/2020 3/13/2020 FAIL
DetailsMelissa Jannusch
Prior to the approval of BLD20-00893 the following revisions are requested:

1. 2 copies of the geotechnical engineering report and any relevant addendums.

2. 1 additional copy of the grading and drainage plan

3. 2 copies of the CFH approval letter from P&Z
Routing - Erosion and Sediment3/12/2020 3/13/2020 PASS
DetailsAndy J. Long
request pool to be under ESC20-00120, issued with BLD permit for associated pool house. Request Approved
Routing Walk-In (Zoning)3/12/20203/12/20203/12/2020ADONE
DetailsSue Cummings
Routing Walk-In (BLD)3/12/20203/12/20203/12/2020APASS
DetailsJosh Bogle
took in for level two revview
Application received 3/12/2020   
Routing - PUBLIC WORKS3/13/2020   FAIL
DetailsMorgan Webb
SEE HILLSIDE FOR FAIL