BLD-Final | 7/16/2020 | 7/17/2020 | 7/17/2020 | P | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher
|
DOC - Permit Finaled | 7/17/2020 | 7/17/2020 | 7/17/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 6/9/2020 | 6/10/2020 | 6/10/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher
|
Plan assigned to (BJM) | 3/16/2020 | 3/16/2020 | 4/15/2020 | | DONE |
Brian McGowan
|
|
|
1st Review Complete-CSN20-00068
|
Routing - PLAN CHECK | 4/15/2020 | | 4/15/2020 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/15/2020 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 4/15/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/15/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/25/2020 | | FAIL |
Brian McGowan
|
|
|
Verify ground snow load. Use Boise City ground/snow loads or provide Special Inspections Form #310 for soils.
|
Routing - PLAN CHECK | 3/25/2020 | | 3/25/2020 | | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 3/25/2020 | | DONE |
Brian McGowan
|
|
|
|
Application received | | | 3/16/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 16 2020 9:16AM
|
First Notice | 7/17/2020 | 7/17/2020 | | | |
Mike Jordan
|
|
|
|