Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD20-00941
StatusIssued
Name VISSER BUILDING CO
Site Address 505 W BANNOCK ST
Project Name505 W Bannock Grading/Found
Customer Number 
ePlanReviewYes
Description
(505 W BANNOCK) (FOUNDATION ONLY) ***PLAN MOD FOR UPDATED STRUCTURAL*** Permit for foundation only. No vertical construction is allowed. Main building permit is BLD20-01095. Work is allowed to be done at the owners risk; any items found not to be in compliance upon approval of the main building plans shall be corrected prior to any further work being completed. Special Inspections required per attached Form 310. MDH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Concrete8/5/20208/6/20208/6/2020PCANC
DetailsDave Hannah
late pm, screened - rebar // Mike Phone #: ###-####
BLD-Concrete7/28/20207/28/20207/28/2020PPART
DetailsDave Hannah
slab on grade ok
BLD-Other7/27/20207/28/20207/28/2020APASS
DetailsDave Hannah
SCREENED // grout... as late as possible // Mike Phone #: ###-####
CHANGE STATUS TO (ISS)  7/22/2020 DONE
OVERRIDE  7/21/2020  
Permit Ready to Issue  7/21/2020 DONE
plan mod
Routing Off Site - STRUCTURAL7/13/2020 7/20/2020 PASS
DetailsMichael Hanson
STAPLEY
PLANS/APPL TAKEN TO FRONT DESK  7/20/2020 DONE
DetailsMichael Hanson
Plan assigned to (M_H)7/1/2020 7/20/2020 DONE
DetailsMichael Hanson
07/08 Plan mod - 505 Bannock
BLD-Footing7/13/20207/14/20207/17/2020PPART
DetailsDave Hannah
Mike *screened* Phone #: ###-#### strct engineer and spec inspection both have ok rebar
BLD-Footing7/10/20207/13/20207/13/2020PPEND
DetailsMike Jordan
Mike *screened* Phone #: ###-####. Grade beams. Noted that wngineer will be on site tomorrow morning to inspect reinforcement as well. Ok pending engineer approval. Stamped city plans not on site at time of inspection.
Plan Modification Accepted  7/1/2020 DONE
just says to see letter that will be submitted
BLD-Footing6/26/20206/29/20206/29/2020APART
DetailsDave Hannah
screened // Mike Phone #: ###-#### needs to resubmit struc foundation plan aproved by struc engineer crew will place conrete at their own risk
BLD-Conference6/26/20206/26/20206/26/2020PDONE
DetailsMike Jordan
Needs to provide approved mix designs for concrete. Also needs to upload plan mod for udated structural sheet S1.11 showing new grade beam layout. Contractor want to place concrete Monday morning June 29th. Noted to contractor (Visser) that they will be placing concrete at their own risk and any non conformances will be repaired or replaced.
BLD-Footing6/11/20206/11/20206/12/2020PPEND
DetailsDave Hannah
Screened- around 3pm, if possible- Jay Phone #: ###-#### ok after spec inspection okls
Issue PAID IN FULL permit  6/1/2020 DONE
Inspection Record Card- Bld  6/1/2020 DONE
Routing Off Site - STRUCTURAL5/21/2020 5/29/2020 PASS
DetailsMichael Hanson
Chris M. @ Stapley engineering
PLANS/APPL TAKEN TO FRONT DESK  5/29/2020 DONE
DetailsMichael Hanson
Permit Ready to Issue  5/29/2020 DONE
ALL MET
METGC Form
METRevised Certificate of Value
METRP
Telephone call  5/29/2020 DONE
Sent email to Angie who will inform Developer of fees due.
Plan assigned to (M_H)3/23/2020 5/29/2020 DONE
DetailsMichael Hanson
1st review completed - 04/28 #502 L3 ePlan - 505 W Bannock Foundation/Grading
Routing PW Drainage5/22/2020 5/22/2020 PASS
DetailsJason C. Taylor
Plan Reviewer's activity  5/14/2020 DONE
DetailsGreg Ruxton
Spoke with Todd Callahan about 120' distance from fire hydrant to FDC Connection. **GJR**
Routing PW Drainage5/12/2020 5/12/2020 FAIL
DetailsJason C. Taylor
Need ACHD approval for Silva Cells in Right of Way. Upload ACHD approved stamped plans. Jason Taylor ###-####
Routing PW Street Lights5/12/2020 5/12/2020 PASS
DetailsTom Marshall
Streetlights will be on BLD20-01095.
Routing PW Sewer Design5/11/2020 5/11/2020 PASS
DetailsDeAnn Brown
Routing - FIRE5/18/20205/18/20205/8/2020 PASS
DetailsGreg Ruxton
Attached comments to case.
Route to Impact Fee Review4/30/20205/3/20205/1/2020 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - FIRE3/18/20203/23/20204/30/2020 FAIL
DetailsGreg Ruxton
Attached comments to case and emailed architect.
1st review completed  4/30/2020 FAIL
DetailsMichael Hanson
Routing - PLAN CHECK3/23/2020 4/29/2020 PASS
DetailsMichael Hanson
Routing PW Environmental3/23/2020 4/10/2020 PASS
DetailsZach Conde
PER ZACH:Grading and foundation plans. PASS
Routing Off Site - STRUCTURAL3/23/2020 4/9/2020 FAIL
DetailsMichael Hanson
Per Chris M. @ Stapley engineering
Routing PW Sewer Design3/23/2020 4/2/2020 FAIL
DetailsDeAnn Brown
See changemarks on sheet C5.00. Note to plug sewer service at the main for the existing service that will not be used.
Routing PW Drainage3/23/2020 3/26/2020 FAIL
DetailsJason C. Taylor
See changemarks in ePlan.
Routing - PLUMBING3/23/2020 3/26/2020 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Design Review3/23/2020 3/26/2020 PASS
DetailsJosh Wilson
Routing - Addressing3/23/2020 3/24/2020 PASS
DetailsDoug Chausow
Routing PW Street Lights3/23/2020 3/24/2020 FAIL
DetailsTom Marshall
Routing PW Solid Waste3/23/2020 3/24/2020 PASS
DetailsEvan Carpenter
Routing - PUBLIC WORKS3/23/2020 3/23/2020 PASS
DetailsMorgan Webb
CORE TO COME THROUGH ON SEPERATE PERMIT.
Routing - PLANNING3/23/2020 3/23/2020 PASS
DetailsKarla Nelson
Current Planning Ok, Design Review sign-off needed.
Intake Approval  3/18/2020  
DetailsJenny Nelson
Application received  3/16/2020 DONE
Application submitted via PDS Online on Mar 16 2020 4:22PM