BLD-Foundation | 6/28/2020 | 6/29/2020 | 6/29/2020 | A | PASS |
Tony Young
|
|
|
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 6/24/2020 | 6/25/2020 | 6/25/2020 | P | PASS |
Tony Young
|
|
|
As early as possible Phone #: 2089655103 >> Inspection requested via mobile web by Alvaro
|
PubWorks Subgrade Approval | 6/25/2020 | 6/25/2020 | 6/25/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Telephone call | | | 6/9/2020 | | DONE |
|
|
|
email applicant to request a 302 form because the number entered in the application is incorrect.
|
Issue PAID IN FULL permit | | | 6/9/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/9/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 4/16/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 3/20/2020 | 3/20/2020 | 4/16/2020 | | DONE |
Rob Patrick
|
|
|
1st Review Complete 04/03 Failed: 04/08 sfd L2 ePlan
|
Routing - PLAN CHECK | 4/16/2020 | | 4/16/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 4/16/2020 | | DONE |
|
|
|
met- NEED
GC
|
1st review completed | | | 4/3/2020 | | FAIL |
Rob Patrick
|
|
|
Correction Req'd
|
Routing - PLAN CHECK | 3/20/2020 | | 4/3/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - FIRE | 3/20/2020 | 3/20/2020 | 4/2/2020 | | PASS |
Lee G Meredith
|
|
|
New SFH
Sprinklers are not required. All measurements are within limits. Suez has provided adequate fire flow for a limited duration. Mo review comments provided.
|
Routing PW Grading-Hillside | 3/20/2020 | | 3/31/2020 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - PLANNING | 3/20/2020 | | 3/24/2020 | | PASS |
Kevin Holmes
|
|
|
Passed, meets conditions of CFH20-00009
|
Routing - Erosion and Sediment | 3/20/2020 | | 3/24/2020 | | PASS |
Michael Zawacki
|
|
|
|
Route to Impact Fee Review | 3/20/2020 | 3/23/2020 | 3/23/2020 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 3/20/2020 | | 3/23/2020 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 3/20/2020 | | PASS |
|
|
|
|
Routing - Addressing | 3/20/2020 | | 3/20/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/20/2020 | | 3/20/2020 | | PASS |
Rita DeYoung
|
|
|
|
Plan Reviewer's activity | | | 3/20/2020 | | DONE |
|
|
|
Emailed Conner Construction to suggest that a increased fire hydrant flow of 1750 gpm with a reduced duration may be available and that they should contact SUEZ to see if it is. This has been the case in other parts of this subdivision. If not available, sprinklers will be required.
4-1-20:Received and updated SUEZ report that indicates 1729 GPM is avalilable for 102 minutes. This is acceptable.
|
Application received | | | 3/16/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 16 2020 4:23PM
|