Permit Information
Permit NumberBLD20-00962
StatusFinaled
Name FRAME PROS LLC
Site Address 1525 S ORCHARD ST
Project NameId Spine and Sport
Customer Number 
ePlanReviewYes
Description
(IDAHO SPINE AND SPORT - NEW TI) **PLAN MODIFICATION 8/3/20 - specifying location of return grill duct detector; reconfiguring parking stalls - one accessible space required. JJN** **PLAN MODIFICATION 6/18/20 - Changing treatment area in middle to open office area and changing second treatment area to patient exercise area.**JJN** Permit for new tenant improvements to an existing 1,856 sq ft building previously occupied as a convenience/gas station. Approval is contingent upon adhering to the approved plans on file. Work to include: Removing one existing bathroom - single unisex bathroom approved using 2018 IBC section 2902 exception 4; constructing select non bearing walls to create an office, exam room, waiting area, employee break room, and open treatment area; new windows on east wall; new suspended tile ceiling; new lighting; electrical work; plumbing work, mechanical work and interior finished in compliance with CH. 8 of the 2015 IBC. This building is not fire sprinklered. **JJN**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  8/12/2020 DONE
BLD-Final8/10/20208/11/20208/11/2020APASS
DetailsTell Riley
Jeff - */Screened/* Phone #: ###-####//corrections have been completed//parking meets site plan//no other work on exterior or parking areas//ACHD email was reviewed onsite//
BLD-Final8/6/20208/6/20208/6/2020PNR
DetailsTell Riley
Jeff - To determine requirements for TCO */Screened*/ Phone #: ###-####//need mechanical final//discussed requirements for accesible restroom, breakroom//accessible parking space needs to meet plans//existing accessible ramp--no new work on exterior//used a conference//
FIRE-Final Inspection8/6/20208/6/20208/6/2020PPASS
DetailsTroy Cobbley
life safety passed.

Jeff - To determine requirements for TCO */Screened*/ Phone #: ###-####
FIRE-Final Inspection8/5/20208/6/20208/6/2020APASS
DetailsTroy Cobbley
life safety passed,

###-####
BLD-Final8/5/20208/6/20208/6/2020ACANC
DetailsTell Riley
Jeff -*/Screened*/ Phone #: ###-####//needs mechanical finaled//need to have grid accessible for inspection//will need ACHD approval for final//
Plan assigned to (J_N)7/28/20207/28/20208/4/2020 DONE
DetailsJenny Nelson
1st complete 08/03 plan mod - failed planning for parking stalls
Routing - Design Review8/4/2020 8/4/2020 PASS
DetailsKatelyn Menuge
Redlined minimum van space ADA dimensions on site plan.
Routing - PLANNING8/4/2020 8/4/2020 PASS
DetailsDavid Moser
Permit Ready to Issue  8/4/2020 DONE
PLAN MOD#2- do not issue
CHANGE STATUS TO (ISS)  8/4/2020 DONE
plan mod
Routing - PLAN CHECK8/3/2020 8/3/2020 PASS
DetailsJenny Nelson
Routing - Design Review8/3/2020 8/3/2020 FAIL
DetailsKatelyn Menuge
Routing - PLANNING8/3/2020 8/3/2020 FAIL
DetailsDavid Moser
With the changes to the parking lot design the site now exceeds the maximum number of parking spaces (Boise City Section 11-7-03.1.A(4)). Since the building is about 2,000 sq. ft. is size administrative planning approval is required to exceed the parking maximum.. Need to variance for parking spaces to encroach into setbacks
Plan Modification Accepted  7/28/2020 DONE
plan mod submitted by Chuck Tookey of Maxey Tookey Architects. As built of striping and location of duct detector. Sheets A1.0 and SP100
BLD-Wall cover6/25/20206/25/20206/25/2020PPASS
DetailsTell Riley
screened - call for access // Sam Phone #: ###-####//ok to cover walls only//call for grid when ready//submit site plan for plan mod prior to final as it does not reflect the current conditions//
BLD-Framing/Rough-in6/22/20206/23/20206/23/2020PPART
DetailsTell Riley
call ahead for access - lockbox - screened // *Jeff/ Sam Phone *###-####// ###-####//CN posted//window framing does not reflect plans or engineering//maintain finished corridor widths per plans//ok to insulate only//
CHANGE STATUS TO (ISS)  6/22/2020 DONE
Plan assigned to (J_N)6/11/20206/11/20206/18/2020 DONE
DetailsJenny Nelson
Routing - PLAN CHECK6/16/2020 6/18/2020 PASS
DetailsJenny Nelson
Permit Ready to Issue  6/18/2020 DONE
Plan Mod Passed
Plan Modification Accepted  6/11/2020 DONE
three areas on the plans called out as treament areas. two of them are not treatment areas. Treatment area 110 is going to be used as office. Treatment area 107 is goint to be used as an exercise area
Issue PAID IN FULL permit  5/28/2020 DONE
Print Occupancy Form  5/28/2020 DONE
Plan assigned to (J_N)4/16/20204/16/20205/22/2020 DONE
Details
1st complete 05/13 Idaho Spine an Sport L-3
Routing - PLAN CHECK5/22/2020 5/22/2020 PASS
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  5/22/2020 DONE
DetailsJenny Nelson
Permit Ready to Issue  5/22/2020 DONE
email permit to: sam@frameprosboise.com
all met:chuck@maxey-tookey.com

NEED
ACHD
GC FORM
REVISED VALUE
Route to Impact Fee Review5/18/20205/21/20205/19/2020 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - FIRE4/16/20204/16/20205/18/2020 PASS
DetailsErika Akin
No comments attached. New fire extinguisher shown on plan sheet A1.0. PDS/Fire Inspector to field verify life safety.
1st review completed  5/18/2020 DONE
DetailsJenny Nelson
Routing Off Site - STRUCTURAL4/16/2020 5/14/2020 PASS
Details
AHJ
Routing - PLAN CHECK4/16/2020 5/14/2020 FAIL
DetailsJenny Nelson
Need site plan for exterior work and showing accessible parking and accessible route
Routing - Erosion and Sediment4/16/2020 4/22/2020 PASS
DetailsMichael Zawacki
TI. Needs to follow good housekeeping with trash and any outside storage
Routing - Design Review4/16/2020 4/17/2020 PASS
DetailsKatelyn Menuge
Routing - PLANNING4/16/2020 4/16/2020 PASS
DetailsDavid Moser
Medical Office use allowed in C-2D zone
Routing - Addressing4/16/2020 4/16/2020 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS4/16/2020 4/16/2020 PASS
DetailsMorgan Webb
Intake Approval  4/10/2020 PASS
Intake Approval  4/2/2020 FAIL
DetailsJenny Nelson
Please provide ACHD letter for change of use/occupancy
Intake Approval  3/18/2020 FAIL
DetailsJavier Guzman
For prescreen review provide and upload the following:
• Provide a completed 520 checklist as this is a change in use (Incomplete submittals will not be accepted
• The checklist is not complete unless all information is filled out, all appropriate boxes are checked and all plan page numbers are listed.
• Provide items that are requested from the checklist that apply to the project. Checklist can be found at https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/?category=all&search=all
• Please make sure that you reach out to ACHD for review on this change of use/occupancy. If additional fees are due, they will need to be paid or paid when the permit is issued. If no fees are due, please submit the documentation from ACDH as such.
• FYI, two restrooms shall be required for an occupant load of 19 per section 2902.2 ex #2
Application received  3/17/2020 DONE
Application submitted via PDS Online on Mar 17 2020 2:22PM
First Notice 8/22/2020