BLD-Framing/Rough-in | 5/27/2020 | 5/28/2020 | 5/28/2020 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by James Greenwood wall bracing ok
|
BLD-Wall Bracing | 5/28/2020 | 5/28/2020 | 5/28/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by James Greenwood
|
BLD-Foundation | 4/29/2020 | 4/30/2020 | 4/30/2020 | P | PASS |
Jim Storey
|
|
|
Screened- stem wall -Francis Phone #: ###-####
|
BLD-Footing | 4/28/2020 | 4/29/2020 | 4/29/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
Issue PAID IN FULL permit | | | 4/24/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 4/23/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 4/7/2020 | 4/7/2020 | 4/23/2020 | | DONE |
Rob Patrick
|
|
|
1st Review Complete 04/15 Failed. 04/20 sfd L1 ePlan
|
Routing - PLAN CHECK | 4/23/2020 | | 4/23/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/23/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 4/23/2020 | | DONE |
|
|
|
met
|
1st review completed | | | 4/15/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
Routing - PLAN CHECK | 4/7/2020 | | 4/15/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
Route to Impact Fee Review | 4/7/2020 | 4/10/2020 | 4/8/2020 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 4/7/2020 | | 4/8/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/7/2020 | | 4/7/2020 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 4/7/2020 | | 4/7/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/7/2020 | | 4/7/2020 | | PASS |
Candy A. Nichols
|
|
|
CREDIT FOR DEMO
|
Intake Approval | | | 4/7/2020 | | PASS |
|
|
|
|
Intake Approval | | | 3/31/2020 | | FAIL |
|
|
|
Plans need to be be uploaded as idividual sheets.
|
Application received | | | 3/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2020 11:03AM
|