BLD-Foundation | 8/3/2020 | 8/7/2020 | 8/7/2020 | P | PART |
Brandon Shaw
|
|
|
Work in progress... Five out of Six units, per this permit...
|
BLD-Footing | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 7/27/2020 | 7/28/2020 | 7/28/2020 | P | NR |
Brandon Shaw
|
|
|
Need Soil subgrade submitted and approved by PW...
|
PubWorks Subgrade Approval | 7/28/2020 | 7/28/2020 | 7/28/2020 | | DONE |
Jason C. Taylor
|
|
|
**ALL 6 FOUNDATIONS***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 7/15/2020 | 7/16/2020 | 7/16/2020 | P | PART |
Brandon Shaw
|
|
|
Scott Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/11/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/11/2020 | | |
|
|
|
|
OVERRIDE | | | 6/10/2020 | | |
|
|
|
|
Plan assigned to (BJM) | 4/15/2020 | 4/15/2020 | 6/10/2020 | | DONE |
Brian McGowan
|
|
|
06/05- 3rd Review Complete - L3 Retaining wall/foundation for subdivision
|
Routing Off Site - STRUCTURAL | 6/10/2020 | | 6/10/2020 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/10/2020 | | 6/10/2020 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2020 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLANNING | 6/10/2020 | | 6/10/2020 | | PASS |
Sue Cummings
|
|
|
|
Permit Ready to Issue | | | 6/10/2020 | | DONE |
|
|
|
MET
NEED RP
NEED GC (ALREADY ON THE APPLICATION)
|
Routing - PLANNING | 6/8/2020 | | 6/8/2020 | | PASS |
Leon Letson
|
|
|
|
Plan Reviewer's activity | | | 6/8/2020 | | DONE |
Brian McGowan
|
|
|
Sent Sarah and Justin an email requesting Sheets A8- Foundation Profiles- be stamped, dated, signed and emailed back to me.
Thought this would be quicker that failing and sending a Task.
|
Routing PW Grading-Hillside | 6/5/2020 | | 6/5/2020 | | PASS |
Jason C. Taylor
|
|
|
No review required. JCT
|
Routing - PLAN CHECK | 5/27/2020 | | 5/27/2020 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLANNING | 5/27/2020 | | 5/27/2020 | | FAIL |
Sue Cummings
|
|
|
The plat needs to be recorded
|
Plan Reviewer's activity | | | 5/27/2020 | | DONE |
Brian McGowan
|
|
|
Applicant requested Task be sent back to them
|
Routing Off Site - STRUCTURAL | 5/26/2020 | | 5/22/2020 | | FAIL |
Brian McGowan
|
|
|
As per KPFF- Corrections Required
|
Routing PW Grading-Hillside | 5/20/2020 | | 5/20/2020 | | PASS |
Melissa Jannusch
|
|
|
Early start foundation permit only. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - PLAN CHECK | 5/12/2020 | | 5/12/2020 | | FAIL |
Brian McGowan
|
|
|
Not all the requested drawings were provided
|
Routing Off Site - STRUCTURAL | 5/12/2020 | | 5/12/2020 | | FAIL |
Brian McGowan
|
|
|
See structural change marks
|
Routing - PLANNING | 5/12/2020 | | 5/12/2020 | | DONE |
Sue Cummings
|
|
|
still no recorded plat
|
Routing PW Grading-Hillside | 5/4/2020 | | 5/4/2020 | | FAIL |
Melissa Jannusch
|
|
|
Grading and Drainage ok. Geotech ok. Needs thrid party review and building department approval for walls prior to hillside approval. --MMJ
|
Routing Off Site - STRUCTURAL | 4/16/2020 | | 4/23/2020 | | FAIL |
Brian McGowan
|
|
|
KPFF- no foundation plans provided
|
Routing - PLANNING | 4/1/2020 | | 4/23/2020 | | FAIL |
Sue Cummings
|
|
|
Has not received final plat approval
|
Routing PW Grading-Hillside | 4/1/2020 | | 4/16/2020 | | FAIL |
Melissa Jannusch
|
|
|
Grading and Drainage ok. Geotech ok. Needs thrid party review and building department approval for walls prior to hillside approval. --MMJ
|
Routing - PLAN CHECK | 4/1/2020 | | 4/16/2020 | | FAIL |
Brian McGowan
|
|
|
Needed to send the task back so they could upload the foundation plans
|
1st review completed | | | 4/16/2020 | | DONE |
Joe Bruce
|
|
|
missing activity
|
Plan assigned to (JAB) Josh | 4/1/2020 | 4/1/2020 | 4/15/2020 | | DEFR |
Josh Bogle
|
|
|
04/07 retaining wall, ePlan - deferred to BJM
|
Routing - Erosion and Sediment | 4/1/2020 | | 4/3/2020 | | PASS |
Andy J. Long
|
|
|
Certified RP provided, plan approved.
|
Routing - PUBLIC WORKS | 4/1/2020 | | 4/1/2020 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/1/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/1/2020 | | DONE |
|
|
|
|
Intake Approval | | | 4/1/2020 | | PASS |
|
|
|
|
Intake Approval | | | 3/24/2020 | | FAIL |
|
|
|
Drawings must be uploaded as individual files. Please re upload the 3 packages as separate files and re submit.
|
Intake Approval | | | 3/23/2020 | | FAIL |
|
|
|
Need
Grading Plan
Geo Tech Report
plans must be individual files
|
Telephone call | | | 3/23/2020 | | DONE |
|
|
|
Spoke with Melissa, she stated she will contact Justin about this project. (Brian or Carl should review this permit and Leon for planning)
|
Application received | | | 3/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2020 12:53PM
|