BLD-Footing | 4/22/2020 | 4/23/2020 | 4/23/2020 | A | PART |
Mike Jordan
|
|
|
crew onsite for early am inspe tion ###-#### wes Phone #: ###-#### Inspection requested via web by Terissa Morain. No city approved plans on site. Contractor to proceed at his own risk. The approved set must be present on final. Any non-compliance issues observed at thjis time will be repaired.
|
Issue PAID IN FULL permit | | | 4/22/2020 | | DONE |
|
|
|
|
Plan assigned to (D_S) Debbie | 4/14/2020 | 4/14/2020 | 4/16/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLANNING | 4/16/2020 | | 4/16/2020 | | PASS |
Crystal Rain
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2020 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 4/16/2020 | | DONE |
|
|
|
met
|
Routing - PLANNING | 4/15/2020 | | 4/15/2020 | | FAIL |
Crystal Rain
|
|
|
Corrections required. Site plan does not reflect required setbacks. Description of project mentions roof-mounted array but submitted documentation reflects only ground equipment.
|
Plan assigned to (JAB) Josh | 4/7/2020 | 4/7/2020 | 4/14/2020 | | DEFR |
Josh Bogle
|
|
|
04/13 PV, ePlan
|
Routing - PLAN CHECK | 4/7/2020 | | 4/14/2020 | | PASS |
Josh Bogle
|
|
|
ESC-No Energy-No
|
1st review completed | | | 4/14/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLANNING | 4/7/2020 | | 4/7/2020 | | FAIL |
Crystal Rain
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/7/2020 | | DONE |
|
|
|
|
Intake Approval | | | 4/7/2020 | | PASS |
|
|
|
|
Application received | | | 3/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2020 3:00PM
|