BLD-Final | 4/27/2020 | 4/28/2020 | 4/28/2020 | A | DONE |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by BRS Permitting
|
DOC - Permit Finaled | 4/28/2020 | 4/28/2020 | 4/28/2020 | P | PASS |
Tony Young
|
|
|
done
|
BLD-Framing/Rough-in | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | DONE |
Jim Storey
|
|
|
Jay Walters is the onsite contact: ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting// No work needed to strengthen the existing roof structure per engineer’s roof evaluation.
|
Issue PAID IN FULL permit | | | 4/1/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/27/2020 | | DONE |
|
|
|
|
Plan assigned to (D_S) Debbie | 3/26/2020 | 3/26/2020 | 3/26/2020 | | DONE |
Debbie Sanine
|
|
|
03/30 PV, ePlan
|
Plan assigned to (JAB) Josh | 3/24/2020 | 3/24/2020 | 3/26/2020 | | DEFR |
Josh Bogle
|
|
|
03/30 PV, ePlan
|
Routing - PLAN CHECK | 3/24/2020 | | 3/26/2020 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 3/26/2020 | | DONE |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLANNING | 3/24/2020 | | 3/24/2020 | | PASS |
Crystal Rain
|
|
|
|
Intake Approval | | | 3/24/2020 | | PASS |
|
|
|
|
Application received | | | 3/23/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 23 2020 2:40PM
|