BLD-Footing | 7/22/2020 | 7/22/2020 | 7/22/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 7/22/2020 | 7/22/2020 | 7/22/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 7/16/2020 | 7/17/2020 | 7/17/2020 | A | NR |
Brandon Shaw
|
|
|
Need geo soil subgrade submitted and approved by PW...
|
BLD-Foundation | 6/4/2020 | 6/5/2020 | 6/5/2020 | A | NR |
Brandon Shaw
|
|
|
Pat *screened* Phone #: ###-####
|
BLD-Footing | 6/4/2020 | 6/4/2020 | 6/4/2020 | P | NR |
Brandon Shaw
|
|
|
Need soil subgrade submitted and approved by PW...
|
Issue PAID IN FULL permit | | | 4/9/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/9/2020 | | DONE |
|
|
|
|
Telephone call | | | 4/9/2020 | | DONE |
|
|
|
4/14 call and left message and email permit again to be sign and return//release eplan
|
Permit Ready to Issue | | | 4/6/2020 | | DONE |
|
|
|
MET- send fee to -aitor@capitollandscape.com
Need GC
|
Plan assigned to (D_S) Debbie | 4/2/2020 | 4/2/2020 | 4/3/2020 | | DONE |
Debbie Sanine
|
|
|
04/03 pergola, ePlan
|
1st review completed | | | 4/3/2020 | | DONE |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - Erosion and Sediment | 3/31/2020 | | 4/3/2020 | | PASS |
Andy J. Long
|
|
|
applicant asking to piggyback on ESC19-00942.
VOID. Okay to be covered by existing ESC permit for the home construction ESC19-00942. Must using neighborhood concrete washout facility.
|
Plan assigned to (JAB) Josh | 3/30/2020 | 3/30/2020 | 4/2/2020 | | DEFR |
Josh Bogle
|
|
|
04/03 pergola, ePlan
|
Routing - PLAN CHECK | 3/30/2020 | | 4/2/2020 | | PASS |
Josh Bogle
|
|
|
ESC - Y and ENERGY - N
|
Routing PW Grading-Hillside | 3/31/2020 | | 4/1/2020 | | PASS |
Melissa Jannusch
|
|
|
Pergola only rest of project is landscaping.
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
Routing - PLANNING | 3/30/2020 | | 3/31/2020 | | PASS |
Jeff Lowe
|
|
|
pergola and landscaping features only. no pool or spa allowed
|
Intake Approval | | | 3/30/2020 | | PASS |
|
|
|
|
Application received | | | 3/23/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 23 2020 4:13PM
|