BLD-Final | 5/22/2020 | 5/26/2020 | 5/26/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Timothy Gammill
|
DOC - Permit Finaled | 5/26/2020 | 5/26/2020 | 5/26/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 5/7/2020 | 5/7/2020 | 5/7/2020 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Timothy Gammill// ok after post/beam hardware
|
BLD-Conference | 4/30/2020 | 4/30/2020 | 4/30/2020 | P | DONE |
Brandon Shaw
|
|
|
Contractor wants to use 2x6 ledger, SDC screws (2) at each stud and joist hangers for patio cover...
|
BLD-Footing | 4/22/2020 | 4/22/2020 | 4/22/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Timothy Gammill
|
Issue PAID IN FULL permit | | | 4/13/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/13/2020 | | DONE |
|
|
|
|
Telephone call | | | 4/13/2020 | | DONE |
|
|
|
email permit and inspection card to- tim@gammillconstructioninc.com
release eplan
|
Plan assigned to (JAB) Josh | 3/27/2020 | 3/27/2020 | 4/9/2020 | | PASS |
Josh Bogle
|
|
|
04/02 patio cover, ePlan - 1st done
|
Routing - PLAN CHECK | 4/9/2020 | | 4/9/2020 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2020 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 4/9/2020 | | DONE |
|
|
|
MET
|
Routing - PLANNING | 4/2/2020 | | 4/2/2020 | | PASS |
Jeff Lowe
|
|
|
|
1st review completed | | | 4/1/2020 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/27/2020 | | 4/1/2020 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan
|
Routing - PLANNING | 3/27/2020 | | 3/30/2020 | | FAIL |
Jeff Lowe
|
|
|
need a site plan to understand setbacks. moreover, setbacks are 10-feet on the side and it does not appear this would be approved.
|
Intake Approval | | | 3/27/2020 | | PASS |
|
|
|
|
Application received | | | 3/26/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 26 2020 3:18PM
|