BLD-Final | 7/28/2020 | 7/28/2020 | 7/28/2020 | P | PASS |
Mike Jordan
|
|
|
screened // Duane Phone #: ###-####
|
FIRE-Final Inspection | 7/28/2020 | 7/28/2020 | 7/28/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Call for access lockbox on door. Dwayne- */Screened*/ *jobsite is vacant Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 7/24/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 7/23/2020 | | |
|
|
|
|
Plan assigned to (M_H) | 6/26/2020 | | 7/23/2020 | | DONE |
Michael Hanson
|
|
|
07/17 Plan Mod Access 2 care EpLAN
|
Routing - PLAN CHECK | 6/26/2020 | | 7/23/2020 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 7/23/2020 | | DONE |
|
|
|
PLAN MOD
|
Plan Modification Accepted | | | 6/26/2020 | | DONE |
|
|
|
EXISTING OFFICE EXISTING TO REMAIN. PLANS TO MODIFY OFFICE AND DIVIDE INTO (2) OFFIES OMITTED FROM PLANS. NEW OFFICE CONSTRUCTED AT DIFFERENT AREA OF SPACE. NEW OFFICE 384.
|
BLD-Final | 6/25/2020 | 6/25/2020 | 6/25/2020 | P | NR |
Mike Jordan
|
|
|
Duane - Altecca Construction Door code 1940 if not there Phone #: ###-#### Inspection requested via web by Duane Seid. Fire/life/afety has failed.
|
FIRE-Final Inspection | 6/25/2020 | 6/25/2020 | 6/25/2020 | P | FAIL |
Troy Cobbley
|
|
|
Provide plan mods for wall changes and provide the exit signs and emergency lightng as shown.
Duane - Altecca Construction Door code 1940 if not there Phone #: ###-#### Inspection requested via web by Duane Seid
|
BLD-Framing/Rough-in | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | PASS |
Mike Jordan
|
|
|
Duane Phone #: ###-####. Interior steel stud framed walls ok.
|
Issue PAID IN FULL permit | | | 4/28/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/28/2020 | | DONE |
|
|
|
|
Telephone call | | | 4/28/2020 | | DONE |
|
|
|
email permit and inpsection card to -Duane@Altecca.com>
|
Routing - PLAN CHECK | 4/23/2020 | | 4/23/2020 | | PASS |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 4/23/2020 | | DONE |
|
|
|
MET Duane Seid
Need GC
Need Revised Values
|
Plan assigned to (M_H) | 4/2/2020 | | 4/23/2020 | | DONE |
Michael Hanson
|
|
|
1st review completed - 04/15 #518 L2 ePlan - ACCESS 2 CARE TI & EXPANSION
|
Route to Impact Fee Review | 4/21/2020 | 4/24/2020 | 4/22/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 4/2/2020 | | 4/21/2020 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
1st review completed | | | 4/21/2020 | | DONE |
Michael Hanson
|
|
|
|
Routing - Addressing | 4/2/2020 | | 4/2/2020 | | PASS |
Doug Chausow
|
|
|
Ste 370
|
Routing - PUBLIC WORKS | 4/2/2020 | | 4/2/2020 | | PASS |
Morgan Webb
|
|
|
NO NEW PLUMBING
|
Intake Approval | | | 3/31/2020 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 3/30/2020 | | FAIL |
Michael Hanson
|
|
|
Provide architect stamp, signed and dated on all sheets
Revise floor plan to include south wall to show full extent of project.
Provide exit signs and emergency lighting information.
|
Application received | | | 3/27/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 27 2020 2:30PM
|