BLD-Footing | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | PASS |
Tony Young
|
|
|
Steel inspection on rebar in pool in back yard. All plans and permits are on site and located near the future pool equipment location. If additional assistance is needed please feel free to call Monica at ###-#### Phone #: ###-#### Inspection requested via web by Monica McNair
|
PubWorks Subgrade Approval | 7/2/2020 | 7/2/2020 | 7/2/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
(F) Reprint permit | | | 5/26/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/26/2020 | | DONE |
|
|
|
|
Telephone call | | | 5/26/2020 | | DONE |
|
|
|
send permit to trowey@ppas.com
|
OVERRIDE | | | 5/22/2020 | | |
|
|
|
|
Plan assigned to (J_N) | 5/19/2020 | 5/19/2020 | 5/22/2020 | | DONE |
Jenny Nelson
|
|
|
pool
|
Routing - Erosion and Sediment | 5/19/2020 | | 5/22/2020 | | PASS |
Michael Zawacki
|
|
|
waiver approved
|
1st review completed | | | 5/22/2020 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 5/22/2020 | | 5/22/2020 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/22/2020 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 5/22/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/22/2020 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 5/8/2020 | 5/8/2020 | 5/19/2020 | | DEFR |
Josh Bogle
|
|
|
05/14 pool, ePlan
|
Routing - PLAN CHECK | 5/8/2020 | | 5/19/2020 | | FAIL |
Jenny Nelson
|
|
|
Barrier requirements not specified on plans
|
Routing PW Grading-Hillside | 5/8/2020 | | 5/18/2020 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. Please allow 24 hours for subgrade approval processing. If you have any questions call Melissa Jannusch ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - PLANNING | 5/8/2020 | | 5/15/2020 | | PASS |
Kevin Holmes
|
|
|
|
Routing - PUBLIC WORKS | 5/8/2020 | | 5/8/2020 | | PASS |
Candy A. Nichols
|
|
|
INGROUND SWIMMING POOL
|
Intake Approval | | | 5/8/2020 | | PASS |
|
|
|
|
Intake Approval | | | 4/3/2020 | | FAIL |
|
|
|
4/2/2020 3rd Prescreen- This is not a new process, the CFH20-00027 needs to be approved by Planning and Zoning (different department than the Building department) when that is approved and the appeal period is over you may submit this for your building permit. You may contact Planning and Zoning for questions on your CFH case and for the appeal process at ###-#### and asked to speak with someone in Planning and Zoning.
|
Intake Approval | | | 4/1/2020 | | FAIL |
|
|
|
Project will require a CAT II Hillside application prior to acceptance of the building permit application. Please finish CFH20-00027. Once the application has been approved by P&Z please upload the approval letter and the appeal period has passed, then this building permit case can be routed for review. Melissa Jannusch Mjannusch@cityofboise.org.
|
Telephone call | | | 3/31/2020 | | DONE |
|
|
|
Emailed applicant to inform them a 426 pool application should of been pulled instead of a new house 404. Asked for him to fill out a 426 application and 302 form.
|
Intake Approval | | | 3/31/2020 | | FAIL |
|
|
|
Need:
1. Grading and drainage plan.
2. Erosion narrative.
3. Erosion and sediment control plan. Or provide a waiver letter
4. Site plan of the whole parcel showing where the pool is located.
5.Project will require a CAT II Hillside application prior to acceptance of the building permit application. Application #114 will need to be filled out and turned in to the Planning & Zoning counter at city hall with the application fee. Once the application has been approved by P&Z please upload the approval letter and then this building permit case can be routed for approval. Melissa Jannusch ###-####.-
|
Application received | | | 3/30/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 30 2020 10:43AM
|