Permanent Occupancy | | | 6/8/2020 | | DONE |
|
|
|
|
BLD-Final | 6/4/2020 | 6/4/2020 | 6/4/2020 | P | PASS |
Tell Riley
|
|
|
screened // Steve Phone #: ###-####//letter from engineer specifying anchor size, and letter from engineer stating that no bolting is required as the equipment is considered as furniture--based on these letters the owner used two bolts to prevent sliding, the engineer did not require this based on the letter from June 1 2020//railing was added with tight chain and permant railing from manufacturer was ordered and will be installed per the owner//
|
(F) Reprint permit | | | 6/4/2020 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 6/3/2020 | | DONE |
|
|
|
Allowed equipment anchors to be installed with out Special Inspection.
|
BLD-Final | 5/29/2020 | 5/29/2020 | 5/29/2020 | P | NR |
Tell Riley
|
|
|
screened // Steve Phone #: ###-####//need to submit engineers letter that removes the requirements for special inspection for anchor bolt attachment to update teh scope of permit//provide clarification on guard at platfom on east corner next to vault as no guard is in place at this location//
|
FIRE-Final Inspection | 5/27/2020 | 5/28/2020 | 5/28/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. The carbon dioxide is under limits for alarm. Steve Phone #: ###-####
|
Telephone call | | | 5/1/2020 | | DONE |
|
|
|
email sent to brewster@bearislandbrewing.com to informed them that not all fees were paid
|
Issue PAID IN FULL permit | | | 5/1/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/1/2020 | | DONE |
|
|
|
|
Routing - FIRE | 4/27/2020 | 4/27/2020 | 4/28/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case.
|
Plan assigned to (CJW) | 4/3/2020 | 4/3/2020 | 4/28/2020 | | PASS |
Carl Westfall
|
|
|
(1st done) 9 - 04/13/20 (L-2 - 7 days) (eplan - 3 sheets) Bear Island Brewing
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/28/2020 | | DONE |
|
|
|
MET Beth Bechtel
NEED
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 4/25/2020 | | 4/27/2020 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 4/25/2020 | | DONE |
Carl Westfall
|
|
|
came back in on a Saturday
|
Route to Impact Fee Review | 4/21/2020 | 4/24/2020 | 4/22/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals requested | | | 4/21/2020 | | DONE |
|
|
|
|
Routing - FIRE | 4/3/2020 | 4/3/2020 | 4/20/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architect.
|
Routing - PLAN CHECK | 4/3/2020 | | 4/20/2020 | | PASS |
Carl Westfall
|
|
|
Drawings approved with referenced plan review report
|
1st review completed | | | 4/20/2020 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 4/3/2020 | | 4/14/2020 | | PASS |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
Routing PW Environmental | 4/3/2020 | | 4/10/2020 | | PASS |
Zach Conde
|
|
|
PR ZACH: Talked with the Bear Island owner, Beth and her Engineer. They said it would be pretty tough for them to install a water meter, and said they have other ways to calculate incoming flows to the production side. Told them that we could require it down the road. Passed on ePlan with this comment: "Approved per discussion with Beth Bechtel." Please pass on Tidemark.
|
Routing - PUBLIC WORKS | 4/3/2020 | | 4/9/2020 | | PASS |
Morgan Webb
|
|
|
PERMIT CAN BE ISSUED WITHOUT AGREEMENT SIGNED.PER ANGELA.
|
Routing - Design Review | 4/3/2020 | | 4/6/2020 | | PASS |
Josh Wilson
|
|
|
|
Intake Approval | | | 4/3/2020 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 3/31/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 31 2020 9:09AM
|
Intake Approval | | | 3/31/2020 | | FAIL |
Julie Romig
|
|
|
Need: 1. On the Form 304, include Trout Architecture's information under the Registered Design Professional section.
2. Form 310 completed, stamped and signed by the structural engineer and signed by the owner for any required special inspections.
3. Mechanical plans the gas lines and the flue from the kettle and specifications for the kettle.
|