Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD20-01120
StatusIssued
Name COLTRIN FINISH CARPENTRY II LLC
Site Address 2929 S COLE RD Unit: 100
Project NameColtrin Finish Carpentry II
Customer Number 
ePlanReviewYes
Description
**(COLTRIN FINISH CARPENTRY- SUITE #100)** Permit is to remodel an existing 9009 sq. ft. tenant space. Approval is contingent upon adhering to the approved plans on file. Work to include: adding non-bearing walls as needed for (1) Office, an Open Office Area, (2) ADA Compliant Restrooms, a Break Room and a wood working fabrication area; electrical work, plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the 2015 IBC. This building is fully Fire Sprinklered with Fire Alarm. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **BJM**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Framing/Rough-in8/5/20208/5/20208/5/2020PPASS
DetailsMike Jordan
Screened- Kim Phone #: ###-####. Interior steel stud framed walls ok. Hardlids also ok pending fire sprinkler rough in inspection.
BLD-Framing/Rough-in7/31/20207/31/20207/31/2020PNR
DetailsMike Jordan
CALL TO MEET SCREENED // Coltrin Phone #: ###-####Needs to resolve mech. issues, and needs electrical rough in inspection.
Issue PAID IN FULL permit  6/11/2020 DONE
Print Occupancy Form  6/11/2020 DONE
Telephone call  6/11/2020 DONE
email permit to -ryan@larsonarchitects.biz and kim.stolworthy@gmail.com
Plan assigned to (BJM)4/9/20204/9/20206/9/2020 DONE
DetailsBrian McGowan
06/03- 1stReview Complete- Coltrin Trim Carpentry L-3
Routing - PLAN CHECK6/9/2020 6/9/2020 PASS
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  6/9/2020 DONE
DetailsBrian McGowan
Permit Ready to Issue  6/9/2020 DONE

MET GC FORM Ryan Drew
MET REVISED VALUE
Routing - MECHANICAL6/2/2020 6/2/2020 PASS
DetailsTroy James
Dust collector to be installed per manufacturer and the IMC, IFC.
Route to Impact Fee Review5/28/20205/31/20205/29/2020 PASS
DetailsShannon Cade
Review requested for Commercial Permit
1st review completed  5/28/2020 DONE
DetailsBrian McGowan
Routing - PLAN CHECK4/9/2020 5/28/2020 FAIL
DetailsBrian McGowan
See Changemarks
Routing - FIRE4/9/20204/9/20205/8/2020 PASS
DetailsGreg Ruxton
Comments attached to case.
Routing - PLANNING4/9/2020 4/14/2020 PASS
DetailsKarla Nelson
Any exterior work will require Design Review. Building is within the Airport Influence Area B- noise sensitive areas of the facility should provide sound insulation.
Routing - PUBLIC WORKS4/9/2020 4/10/2020 PASS
DetailsMorgan Webb
Routing - Addressing4/9/2020 4/9/2020 PASS
DetailsDoug Chausow
Routing - MECHANICAL4/9/2020 4/9/2020 PASS
DetailsTroy James
Routing - PLUMBING4/9/2020 4/9/2020 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Intake Approval  4/6/2020 PASS
Plan Reviewer's activity  4/2/2020 PASS
Plan intake review passed. It is identified as a warehouse. Confirm that it will not be a wood working shop. If it is, dust collection could be required.
Application received  4/1/2020 DONE
Application submitted via PDS Online on Apr 1 2020 1:22PM