BLD-Framing/Rough-in | 8/5/2020 | 8/5/2020 | 8/5/2020 | P | PASS |
Mike Jordan
|
|
|
Screened- Kim Phone #: ###-####. Interior steel stud framed walls ok. Hardlids also ok pending fire sprinkler rough in inspection.
|
BLD-Framing/Rough-in | 7/31/2020 | 7/31/2020 | 7/31/2020 | P | NR |
Mike Jordan
|
|
|
CALL TO MEET SCREENED // Coltrin Phone #: ###-####Needs to resolve mech. issues, and needs electrical rough in inspection.
|
Issue PAID IN FULL permit | | | 6/11/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/11/2020 | | DONE |
|
|
|
|
Telephone call | | | 6/11/2020 | | DONE |
|
|
|
email permit to -ryan@larsonarchitects.biz and kim.stolworthy@gmail.com
|
Plan assigned to (BJM) | 4/9/2020 | 4/9/2020 | 6/9/2020 | | DONE |
Brian McGowan
|
|
|
06/03- 1stReview Complete- Coltrin Trim Carpentry L-3
|
Routing - PLAN CHECK | 6/9/2020 | | 6/9/2020 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/9/2020 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/9/2020 | | DONE |
|
|
|
MET GC FORM Ryan Drew
MET REVISED VALUE
|
Routing - MECHANICAL | 6/2/2020 | | 6/2/2020 | | PASS |
Troy James
|
|
|
Dust collector to be installed per manufacturer and the IMC, IFC.
|
Route to Impact Fee Review | 5/28/2020 | 5/31/2020 | 5/29/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/28/2020 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 4/9/2020 | | 5/28/2020 | | FAIL |
Brian McGowan
|
|
|
See Changemarks
|
Routing - FIRE | 4/9/2020 | 4/9/2020 | 5/8/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case.
|
Routing - PLANNING | 4/9/2020 | | 4/14/2020 | | PASS |
Karla Nelson
|
|
|
Any exterior work will require Design Review. Building is within the Airport Influence Area B- noise sensitive areas of the facility should provide sound insulation.
|
Routing - PUBLIC WORKS | 4/9/2020 | | 4/10/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 4/9/2020 | | 4/9/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 4/9/2020 | | 4/9/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 4/9/2020 | | 4/9/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 4/6/2020 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 4/2/2020 | | PASS |
|
|
|
Plan intake review passed. It is identified as a warehouse. Confirm that it will not be a wood working shop. If it is, dust collection could be required.
|
Application received | | | 4/1/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 1 2020 1:22PM
|