BLD-Framing/Rough-in | 7/7/2020 | 7/7/2020 | 7/7/2020 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ken Litzinger// garage ok,, may need to add back porch cover and shade cover to the permit
|
BLD-Wall Bracing | 6/10/2020 | 6/11/2020 | 6/11/2020 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ken Litzinger// ok after renail some areas
|
BLD-Foundation | 5/28/2020 | 5/29/2020 | 5/29/2020 | A | PART |
Tony Young
|
|
|
Ken; Phone #: ###-####// work in progress
|
BLD-Footing | 5/28/2020 | 5/28/2020 | 5/28/2020 | P | PASS |
Tony Young
|
|
|
Ken; Phone #: ###-####// setbacks per plan,, footing per plan
|
Issue PAID IN FULL permit | | | 5/4/2020 | | DONE |
|
|
|
|
Telephone call | | | 5/1/2020 | | DONE |
|
|
|
email GC that we still need an RP for this job.
|
OVERRIDE | | | 4/23/2020 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 4/13/2020 | 4/13/2020 | 4/23/2020 | | PASS |
Josh Bogle
|
|
|
04/17 garage, ePlan
|
Routing - PLAN CHECK | 4/15/2020 | | 4/23/2020 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 4/23/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/23/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 4/23/2020 | | DONE |
|
|
|
MET
|
Routing - PLANNING | 4/13/2020 | | 4/13/2020 | | PASS |
Michaella Owens
|
|
|
DRH20-00030
|
Plans ACCEPTED BY PLAN TECH | | | 4/13/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/13/2020 | | DONE |
|
|
|
|
Intake Approval | | | 4/13/2020 | | PASS |
|
|
|
|
Application received | | | 4/10/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 10 2020 1:26PM
|