BLD-Framing/Rough-in | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PART |
Brandon Shaw
|
|
|
Need trades...
|
CHANGE STATUS TO (ISS) | | | 7/20/2020 | | DONE |
|
|
|
|
Plan assigned to (J_N) | 7/8/2020 | 7/8/2020 | 7/17/2020 | | DONE |
Jenny Nelson
|
|
|
07/16 Plan modification Boulder Barber
|
Routing - PLAN CHECK | 7/17/2020 | | 7/17/2020 | | PASS |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 7/17/2020 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
Routing - PLAN CHECK | 7/8/2020 | | 7/16/2020 | | FAIL |
Jenny Nelson
|
|
|
Plans need to show only work that will be done under this permit
|
Routing - MECHANICAL | 7/16/2020 | | 7/16/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 7/16/2020 | | 7/16/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Plan Modification Accepted | | | 7/8/2020 | | DONE |
|
|
|
Changing station layout to comply with Covid-19 regulations
A0, A0.2, A1, A4, A5, A7, E2, E3, M1, P1, P2
|
Issue PAID IN FULL permit | | | 7/2/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/2/2020 | | DONE |
|
|
|
|
Telephone call | | | 6/29/2020 | | DONE |
|
|
|
Wants to submit for a plan modification. Permit hasn't been issued yet. Will issue permit then submit plan mod at a later time
|
Route to Impact Fee Review | 6/22/2020 | 6/25/2020 | 6/23/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (J_N) | 5/26/2020 | 5/26/2020 | 6/22/2020 | | DONE |
|
|
|
06/22 Bolder Barber Shop L-3
|
Routing - PLAN CHECK | 5/26/2020 | | 6/22/2020 | | PASS |
|
|
|
|
1st review completed | | | 6/22/2020 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2020 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 6/22/2020 | | DONE |
|
|
|
MET Jason Buss
GC
REV VALUES
|
Routing - MECHANICAL | 6/19/2020 | | 6/19/2020 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 5/26/2020 | 5/26/2020 | 6/15/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
Routing - PLANNING | 5/26/2020 | | 6/3/2020 | | PASS |
David Moser
|
|
|
|
Routing - MECHANICAL | 5/26/2020 | | 5/28/2020 | | FAIL |
Troy James
|
|
|
Emailed correction to Applicant.
|
Routing - Addressing | 5/26/2020 | | 5/27/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/26/2020 | | 5/27/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 5/26/2020 | | 5/26/2020 | | PASS |
Dan Ediger
|
|
|
per plans and ISPC
|
Intake Approval | | | 5/22/2020 | | |
|
|
|
|
Intake Approval | | | 4/14/2020 | | FAIL |
Jenny Nelson
|
|
|
1. First time tenant build outs in a new building are required to submit a 520 application. Please complete a 520 submittal checklist. It can be found online here: https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/commercial-construction-500/520-major-tenant-improvement/
2. Per 520 submittal checklist please provide site specific fire flow letter.
3. Please reach out to ACHD as license agreement may be required.
|
Application received | | | 4/13/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 13 2020 7:58AM
|