BLD-Final | 5/28/2020 | 5/29/2020 | 5/29/2020 | A | PASS |
Brandon Shaw
|
|
|
Lockbox is on door to the south. 7777. Spoke with inspector. Said we could get a temporary C of O until the siding arrives for the exterior. Interior work in bedroom is finished. Electrical is finished. Phone #: ###-#### Inspection requested via web by Jeremy Howard
|
DOC - Permit Finaled | 5/29/2020 | 5/29/2020 | 5/29/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Framing/Rough-in | 5/12/2020 | 5/13/2020 | 5/13/2020 | A | PASS |
Brandon Shaw
|
|
|
Drywall was removed in north east corner bedroom due to smoke and fire damage. Smoke sealant has been applied, ready to cover. Lock box on the exterior door to the south east; code is 7777. Lockbox can stick slightly. Phone #: ###-#### Inspection requested via web by Jeremy Howard
|
Issue PAID IN FULL permit | | | 4/28/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/28/2020 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 4/15/2020 | 4/15/2020 | 4/27/2020 | | PASS |
Josh Bogle
|
|
|
04/21 fire repair, ePlan
|
1st review completed | | | 4/27/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2020 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 4/27/2020 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 4/15/2020 | | 4/27/2020 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLANNING | 4/15/2020 | | 4/15/2020 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/15/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/15/2020 | | DONE |
|
|
|
|
Intake Approval | | | 4/15/2020 | | PASS |
|
|
|
|
Application received | | | 4/14/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 14 2020 12:00PM
|