BLD-Foundation | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | PASS |
Mike Jordan
|
|
|
Shawn - */ Screened */ Phone #: ###-####
|
BLD-Concrete | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | PASS |
Mike Jordan
|
|
|
Rebar Inspection Phone #: ###-#### Inspection requested via web by Richard Wilson
|
BLD-Concrete | 8/11/2020 | 8/11/2020 | 8/11/2020 | P | FAIL |
Tell Riley
|
|
|
screened - rebar // Shawn Phone #: ###-####//need to add rebar mat under drains in center of pool per the details//need to add bar around skimmers in all locations per the details on the approved plans//
|
Issue PAID IN FULL permit | | | 6/8/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/8/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/1/2020 | | DONE |
|
|
|
MET Greg Beall
Need
GC Form
Revised Cert of Value
|
Plan assigned to (CJW) | 5/4/2020 | 5/4/2020 | 5/29/2020 | | PASS |
Carl Westfall
|
|
|
(1st done) 9 - 05/15/20 (L-3 - 15 days) (eplan - 67 sheets) Goldfish Swim School (routed to Plumbing)
|
Routing - PLUMBING | 5/28/2020 | | 5/29/2020 | | PASS |
Daryl Spivey
|
|
|
Vent FD-1's as required by ISPC
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/27/2020 | | 5/28/2020 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 5/27/2020 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/22/2020 | | DONE |
|
|
|
|
Routing - FIRE | 5/4/2020 | 5/4/2020 | 5/21/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
1st review completed | | | 5/21/2020 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/4/2020 | | 5/20/2020 | | PASS |
Carl Westfall
|
|
|
Chris Holladay (AHJ) swimming pool only
|
Routing - PLAN CHECK | 5/4/2020 | | 5/20/2020 | | PASS |
Carl Westfall
|
|
|
Passed with referenced code sections.
|
Routing PW Environmental | 5/8/2020 | | 5/8/2020 | | PASS |
Zach Conde
|
|
|
PER ZACH: Passed on ePlan with no comments. Please pass on Tidemark.
|
Routing - PUBLIC WORKS | 5/4/2020 | | 5/8/2020 | | PASS |
Morgan Webb
|
|
|
CONTACT WEST BOISE SEWER DISTRICT
|
Routing - Erosion and Sediment | 5/4/2020 | | 5/8/2020 | | PASS |
Michael Zawacki
|
|
|
Site permit issued under esc20-00388
|
Routing - PLANNING | 5/4/2020 | | 5/7/2020 | | PASS |
Ethan Mansfield
|
|
|
|
Routing - MECHANICAL | 5/4/2020 | | 5/5/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 5/4/2020 | | 5/5/2020 | | FAIL |
Daryl Spivey
|
|
|
S-1 and FD-1 shall drain to sanitary not to deck drain piping as shown on P.101
|
Routing - Addressing | 5/4/2020 | | 5/4/2020 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 4/27/2020 | | PASS |
|
|
|
|
Intake Approval | | | 4/15/2020 | | FAIL |
Jenny Nelson
|
|
|
1. Completed 304 Registered Design Professional form
2. As indicated as being provided on submittal checklist please upload planning approval letter, hazardous material list, and ESC waiver request.
3. Site plan as indicated on submittal checklist
4. Structural calculations as indicated on submittal checklist
5. Please specify on checklist which sheet accessibility information can be found on
6. Provide lighting compliance as indicated on submittal checklist
|
Application received | | | 4/14/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 14 2020 12:46PM
|