FIRE-Conference | 7/27/2020 | 7/28/2020 | 7/28/2020 | A | DONE |
Troy Cobbley
|
|
|
Myself, the general contractor, sprinkler contractor and fire alarm contractor went over various requirements for final sign offs. I noted that the fire protection systems in the vacant side of the building will need to be code compliant and operational prior to any final sign offs.\ Jerimih *screened* Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/7/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/7/2020 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 5/11/2020 | | 6/22/2020 | | DONE |
Michael Hanson
|
|
|
3rd review completed - 05/21 #518 L2 ePlan - Hobby Lobby
|
Routing - PLAN CHECK | 6/22/2020 | | 6/22/2020 | | FAIL |
Michael Hanson
|
|
|
The entire #310 form must be uploaded. Only the coversheet was uploaded.
|
Routing - PLAN CHECK | 6/22/2020 | | 6/22/2020 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 6/22/2020 | | DONE |
|
|
|
(kimberly.wilson@hobbylobby.com)
ALL MET
GC FORM
REVISED VALUE
|
Route to Impact Fee Review | 5/29/2020 | 6/1/2020 | 6/1/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan Reviewer's activity | | | 5/28/2020 | | DONE |
Michael Hanson
|
|
|
Changed from 518 to 520 due to scope of work, project complexity, and occupant loading considerations.
|
1st review completed | | | 5/28/2020 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 5/11/2020 | | 5/28/2020 | | FAIL |
Michael Hanson
|
|
|
Just missing the #310 special inspection form. See plan review report for additional information.
|
Routing Off Site - STRUCTURAL | 5/11/2020 | | 5/24/2020 | | PASS |
Michael Hanson
|
|
|
Per D. Haugland @ AHJ engineering
|
Routing - FIRE | 5/11/2020 | 5/11/2020 | 5/20/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
Routing - MECHANICAL | 5/11/2020 | | 5/11/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 5/11/2020 | | 5/11/2020 | | PASS |
Daryl Spivey
|
|
|
See redline notes P0.2 and P0.4. Per plan and ISPC
|
Routing - PUBLIC WORKS | 5/11/2020 | | 5/11/2020 | | PASS |
Morgan Webb
|
|
|
CONTACT WEST BOISE SEWER DISTRICT
|
Routing - Design Review | 5/11/2020 | | 5/11/2020 | | PASS |
Michaella Owens
|
|
|
|
Intake Approval | | | 5/8/2020 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 4/15/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 15 2020 10:26AM
|