BLD-Other | 7/23/2020 | 7/24/2020 | 7/24/2020 | P | PASS |
Brandon Shaw
|
|
|
*Screened* Rebar - Justin Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/23/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/23/2020 | | DONE |
|
|
|
|
Telephone call | | | 7/21/2020 | | DONE |
|
|
|
emailed justin@idahopools.com about rp and fees
|
OVERRIDE | | | 7/17/2020 | | |
|
|
|
|
Plan assigned to (J_N) | 7/1/2020 | 7/1/2020 | 7/17/2020 | | DONE |
Jenny Nelson
|
|
|
1st complete 06/22/20 (L-3 - 15 days) (eplan - 21 sheets) Village East Apartments Pool. Reassigned to Jenny from Carl Westfall's List on 7/1/20.
|
Routing - PLAN CHECK | 7/17/2020 | | 7/17/2020 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/2020 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 7/17/2020 | | DONE |
|
|
|
met
Need
RP
|
Routing - FIRE | 7/14/2020 | 7/14/2020 | 7/16/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
Routing - PLAN CHECK | 7/14/2020 | | 7/15/2020 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - FIRE | 7/7/2020 | 7/7/2020 | 7/14/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architect.
|
Routing - PLAN CHECK | 7/7/2020 | | 7/8/2020 | | FAIL |
Jenny Nelson
|
|
|
No building corrections
|
1st review completed | | | 7/2/2020 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 6/4/2020 | | 7/2/2020 | | FAIL |
Jenny Nelson
|
|
|
|
Plan assigned to (CJW) | 6/4/2020 | 6/29/2020 | 7/1/2020 | | DEFR |
Carl Westfall
|
|
|
9 - 06/22/20 (L-3 - 15 days) (eplan - 21 sheets) Village East Apartments Pool - Reassigned to Jenny Nelson on 7/1/20.
|
Routing PW Environmental | 6/11/2020 | | 7/1/2020 | | PASS |
|
|
|
Passed in ePlan by Zach Conde
|
Routing - FIRE | 6/4/2020 | 6/4/2020 | 6/17/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architect.
|
Routing PW Drainage | 6/11/2020 | | 6/17/2020 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 6/4/2020 | | 6/11/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 6/4/2020 | | 6/8/2020 | | PASS |
Leon Letson
|
|
|
parking pad must be a miniium of 20' from front setback and 15' from street side setback.
|
Routing - Addressing | 6/4/2020 | | 6/8/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - Erosion and Sediment | 6/4/2020 | | 6/5/2020 | | PASS |
Michael Zawacki
|
|
|
Will inspect pool while on site. Pool does need its own permit.
No RP required, prime contractor always on site.
|
Routing - Design Review | 6/4/2020 | | 6/5/2020 | | PASS |
Josh Wilson
|
|
|
|
Routing - MECHANICAL | 6/4/2020 | | 6/5/2020 | | PASS |
Troy James
|
|
|
Field verify pool heaters installation per manufacturer and IMC.
|
Routing - PLUMBING | 6/4/2020 | | 6/5/2020 | | PASS |
Daryl Spivey
|
|
|
Plumbing plan for clubhouse only. Pool not reviewed on this plan.
|
Intake Approval | | | 6/2/2020 | | PASS |
|
|
|
|
Intake Approval | | | 5/26/2020 | | FAIL |
Jenny Nelson
|
|
|
1. ESC plan indicated on submittal checklist as being provided, do not see in plan sheets, please upload.
2. No cover sheet G.01 provided as indicated on submittal checklist, please upload. Also please make sure code analysis is provided - do not see on Sheet PL-0.1
3. Per submittal checklist provide list of chemicals and amounts that will be stored for pool - indicated as provided but do not see included in plans or documents
4. Per submittal checklist plumbing plans must be stamped by Idaho licensed plumbing engineer. Or provide approval from plumbing plan reviewer that stamp not required - can email Dan Ediger at dediger@cityofboise.org to request approval to submit without stamp.
5. Shotcrete is specified on engineering plans - may required special inspections - please have engineer fill out #310 Special Inspections form. Can be found here: https://www.cityofboise.org/media/9063/final310_special_inspections_01-2019.pdf
6. Please make sure stamping area is provided in bottom right corner for city stamp on all plan sheets - cover sheet shall have 4"x4" area 3" off the right edge; and all other sheets shall have 4"x2" area 3" off right edge reserved.
|
Intake Approval | | | 4/27/2020 | | FAIL |
Jenny Nelson
|
|
|
To complete this application please provide the following:
1. Please upload completed submittal checklist, it may be found on the city website here: https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/commercial-construction-500/538-commercial-swimming-pool-and-spa-in-ground/
2. Provide all required documents per the submittal checklist
3. Please provide stamping area at bottom right corner on all plan sheets.
|
Application received | | | 4/16/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 16 2020 2:51PM
|