BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 | P | PASS |
Tell Riley
|
|
|
truss repair document reviewed//putty pad added to recepticles per the super, fire cualk was used at wall penetrations//ok to cover//
|
BLD-Framing/Rough-in | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle***per Carl M. no rated exterior walls or soffits required due to common lots around all garages and the plat***
//provide truss engineering for trusses that appear to have been repaired in the field with gussets//low voltage ELE boxes for garage door sensors in the 2 hr wall, same stud bay will need to be protected per IRC 302.4.2// //any through penetrations through the 2 hr walls need to be firestop protected in accordance with IRC R302.4.1.2//
|
BLD-Wall Bracing | 7/5/2020 | 7/6/2020 | 7/6/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Foundation | 6/7/2020 | 6/8/2020 | 6/8/2020 | A | PART |
Tell Riley
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo //measured setbacks from pins//need to adjust foundation to exact 2' setback on all sides//discussed with contact onsite and working on this when I left//hold downs and some forms still WIP//
|
BLD-Footing | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | PART |
Tell Riley
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru //WIP//pins set to measure 2' setback per the plat//met Ricardo and measured earlier today--crew will set strings at 2' setback for foundation inspection to confirm setbacks//
|
BLD-Footing | 6/1/2020 | 6/2/2020 | 6/1/2020 | A | CANC |
Tell Riley
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo
|
Issue PAID IN FULL permit | | | 5/28/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/28/2020 | | DONE |
|
|
|
|
Telephone call | | | 5/26/2020 | | DONE |
|
|
|
MET
Sent email to CBH Homes npermitting@cbhhomes.com
|
OVERRIDE | | | 5/21/2020 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 4/23/2020 | 4/23/2020 | 5/21/2020 | | PASS |
Josh Bogle
|
|
|
04/29 garage, ePlan - 1st done
|
Routing - PLAN CHECK | 5/21/2020 | | 5/21/2020 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/21/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 5/21/2020 | | DONE |
|
|
|
MET
RP
|
Plan Reviewer's activity | | | 5/13/2020 | | DONE |
Josh Bogle
|
|
|
accepted resubmittal, running it by Legal
|
Routing - PLAN CHECK | 4/23/2020 | | 5/8/2020 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan
|
1st review completed | | | 5/8/2020 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 4/23/2020 | | 4/28/2020 | | PASS |
Kevin Holmes
|
|
|
Passed, meets requirements of PUD18-00052.
|
Intake Approval | | | 4/23/2020 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/23/2020 | | DONE |
|
|
|
|
Intake Approval | | | 4/20/2020 | | FAIL |
|
|
|
Please provide full site plan showing location of garages adjacent to the other buildings, sidewalks, streets, etc
|
Application received | | | 4/17/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 17 2020 10:24AM
|
Intake Approval | | | 4/17/2020 | | FAIL |
|
|
|
applicant requested prescreen fail so that they could finish uploading documents
|