BLD-Footing | 6/22/2020 | 6/22/2020 | 6/22/2020 | P | PART |
Mike Jordan
|
|
|
Bill *screened* Phone #: ###-####
|
Telephone call | | | 6/16/2020 | | DONE |
|
|
|
emailed owner about ESC fees
|
Issue PAID IN FULL permit | | | 6/16/2020 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 4/20/2020 | 4/20/2020 | 6/15/2020 | | PASS |
Josh Bogle
|
|
|
04/24 shop, ePlan - 1st done
|
Routing - PLANNING | 6/15/2020 | | 6/15/2020 | | PASS |
Nicolette Womack
|
|
|
The driveway shall be under 33’ in width in the front yard setback.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/15/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 6/15/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/11/2020 | | 6/11/2020 | | PASS |
Josh Bogle
|
|
|
|
Plan Reviewer's activity | | | 5/14/2020 | | DONE |
Josh Bogle
|
|
|
accepted and routed resubmittal
|
1st review completed | | | 5/1/2020 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | | 4/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 20 2020 9:59AM
|
Plans ACCEPTED BY PLAN TECH | | | 4/20/2020 | | DONE |
|
|
|
|
Intake Approval | | | 4/20/2020 | | PASS |
|
|
|
|
Routing - PLANNING | 4/20/2020 | | 4/20/2020 | | FAIL |
Sue Cummings
|
|
|
waiting on a variance The building permit cannot be issued until 10 days after approval of the variance
|
Routing - PLAN CHECK | 4/20/2020 | | | | FAIL |
Josh Bogle
|
|
|
no review pending Planning approval
|