BLD-Final | 6/10/2020 | 6/16/2020 | 6/16/2020 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by BRS Permitting
|
DOC - Permit Finaled | 6/16/2020 | 6/16/2020 | 6/16/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 6/3/2020 | 6/4/2020 | 6/4/2020 | A | PASS |
Jim Storey
|
|
|
Jay Walters is the onsite contact - ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting No work needed to strengthen the existing roof structure per engineer’s roof evaluation. All racking, modules, and other listed equipment must be installed by a certified
|
Issue PAID IN FULL permit | | | 5/1/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/24/2020 | | DONE |
|
|
|
MET
|
Plan assigned to (D_S) Debbie | 4/23/2020 | 4/23/2020 | 4/23/2020 | | DONE |
Debbie Sanine
|
|
|
|
Plan assigned to (JAB) Josh | 4/20/2020 | 4/20/2020 | 4/23/2020 | | DEFR |
Josh Bogle
|
|
|
04/24 PV, ePlan
|
Routing - PLAN CHECK | 4/20/2020 | | 4/23/2020 | | PASS |
Josh Bogle
|
|
|
Energy-No ESC-No
|
1st review completed | | | 4/23/2020 | | DONE |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/23/2020 | | DONE |
Debbie Sanine
|
|
|
|
Application received | | | 4/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 20 2020 2:19PM
|
Intake Approval | | | 4/20/2020 | | PASS |
|
|
|
|
Routing - PLANNING | 4/20/2020 | | 4/20/2020 | | PASS |
Jeff Lowe
|
|
|
|