BLD-Footing | 7/28/2020 | 7/30/2020 | 7/31/2020 | P | PEND |
Dave Hannah
|
|
|
jason *screened* Phone #: ###-#### ok after spec inspection sign off
|
CHANGE STATUS TO (ISS) | | | 7/23/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 7/8/2020 | | |
|
|
|
|
Plan assigned to (JAR) | 7/2/2020 | 7/6/2020 | 7/8/2020 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - Plan Mod 5th & Grove Foundation
|
Routing - PLAN CHECK | 7/8/2020 | | 7/8/2020 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 7/8/2020 | | DONE |
|
|
|
MET *PLAN MOD DO NOT REISSUE*
|
Routing - PLAN CHECK | 7/6/2020 | | 7/6/2020 | | FAIL |
Julie Romig
|
|
|
Plan mod to clarify scope of work for foundation/podium superstructure
|
Plan Modification Accepted | | | 7/2/2020 | | DONE |
|
|
|
level 1 slab on grade and below slab utility work will not be included with permit
|
Issue PAID IN FULL permit | | | 6/10/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/10/2020 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 5/29/2020 | 6/1/2020 | 6/1/2020 | | DONE |
Julie Romig
|
|
|
|
Routing - FIRE | 5/29/2020 | 5/29/2020 | 6/1/2020 | | PASS |
Erika Akin
|
|
|
Passed per ePlanReview
|
Routing Off Site - STRUCTURAL | 6/1/2020 | | 6/1/2020 | | PASS |
Julie Romig
|
|
|
Passed per ePlanReview BLD19-04924
|
Routing PW Drainage | 6/1/2020 | | 6/1/2020 | | PASS |
Jason C. Taylor
|
|
|
Passed per ePlanReview BLD19-04924
|
Routing PW Sewer Design | 6/1/2020 | | 6/1/2020 | | PASS |
DeAnn Brown
|
|
|
Passed per ePlanReview BLD19-04924
|
Routing - Design Review | 6/1/2020 | | 6/1/2020 | | PASS |
Josh Wilson
|
|
|
Passed per ePlanReview BLD19-04924
|
Routing - PLANNING | 6/1/2020 | | 6/1/2020 | | PASS |
David Moser
|
|
|
Passed per ePlanReview BLD19-04924
|
Routing - PUBLIC WORKS | 6/1/2020 | | 6/1/2020 | | PASS |
Morgan Webb
|
|
|
Passed per ePlanReview BLD19-04924
|
Routing - Erosion and Sediment | 6/1/2020 | | 6/1/2020 | | PASS |
Michael Zawacki
|
|
|
Passed per ePlanReview BLD19-04924
|
Routing PW Environmental | 6/1/2020 | | 6/1/2020 | | PASS |
Rick Christenson
|
|
|
Passed per ePlanReview BLD19-04924
|
1st review completed | | | 6/1/2020 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/1/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/1/2020 | | DONE |
|
|
|
met; Need RP
MET
GC
REV VALUES
|
Routing - PLAN CHECK | 5/29/2020 | | 6/1/2020 | | PASS |
Julie Romig
|
|
|
Foundation only; no building plan review
|
Intake Approval | | | 5/29/2020 | | PASS |
Julie Romig
|
|
|
|
Application received | | | 4/23/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 23 2020 2:37PM
|