FIRE-Final Inspection | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PASS |
Troy Cobbley
|
|
|
life safety passed. Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Ceiling Grid Inspection | 7/30/2020 | 7/31/2020 | 7/31/2020 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Doug Storey//grid looks ok//Electrical passed//new RTU in end classroom will need to be inspected when installed//pending fire sprinkler approval//
|
BLD-Conference | 7/16/2020 | 7/17/2020 | 7/17/2020 | A | DONE |
Tell Riley
|
|
|
Please call 30 min. prior to make sure we are onsite. Thank you. Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Wall Bracing | 7/10/2020 | 7/10/2020 | 7/10/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Doug Storey//scope of permit needs to be updated to remove the phase of work for the auditorium//inspection is on the five classrooms only//wall brackets installed, located on opposite side of previously installed wall brackets to brace the CMU as directed by the architect//no structural details were provided for these brackets//appear to meet sizes per the plans//special inspections were completed for the anchors//
|
Inspection Record Card- Bld | | | 7/10/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/29/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/29/2020 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 5/13/2020 | 5/13/2020 | 6/4/2020 | | DONE |
Julie Romig
|
|
|
06/04 - 2nd Rev - **EXPEDITED REVIEW** Capital High School
|
Routing - PLAN CHECK | 5/29/2020 | | 6/4/2020 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/4/2020 | | DONE |
|
|
|
***HAS TO BE ISSUED WITH EARLY START BLD20-01618*****
MET bgrote@beniton.com
Need GC
Need Revised Values
****EARLY START MUST BE PAID FOR AND ISSUED***
|
Route to Impact Fee Review | 5/26/2020 | 5/29/2020 | 5/27/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/26/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 5/13/2020 | | 5/26/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing - ELECTRICAL | 5/13/2020 | | 5/26/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing - FIRE | 5/13/2020 | 5/13/2020 | 5/22/2020 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - Erosion and Sediment | 5/13/2020 | | 5/22/2020 | | PASS |
Michael Zawacki
|
|
|
TI inside school, no esc required. Please keep any outside storage clean.
|
Routing - Design Review | 5/13/2020 | | 5/15/2020 | | PASS |
Katelyn Menuge
|
|
|
No DR Overlay
|
Routing - PLUMBING | 5/13/2020 | | 5/14/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC
|
Routing - PUBLIC WORKS | 5/13/2020 | | 5/14/2020 | | PASS |
Morgan Webb
|
|
|
CONTACT WEST BOISE SEWER DISTRICT
|
Routing - MECHANICAL | 5/13/2020 | | 5/13/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/13/2020 | | 5/13/2020 | | PASS |
Ethan Mansfield
|
|
|
|
Routing - Addressing | 5/13/2020 | | 5/13/2020 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 5/11/2020 | | PASS |
|
|
|
|
Intake Approval | | | 5/4/2020 | | FAIL |
Jenny Nelson
|
|
|
To complete this application please provide the following:
1. This will need to be submitted as a 520 major tenant improvement, please upload a completed 520 submittal checklist. It can be found here: https://www.cityofboise.org/media/9949/520_major-ti-submittal-checklist.pdf
2. Please provide site specific fire flow letter.
3. Please upload structural calculations - indicated on submittal checklist but do not see in documents.
|
Application received | | | 4/28/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 28 2020 8:32AM
|