BLD-Framing/Rough-in | 6/9/2020 | 6/10/2020 | 6/10/2020 | P | PASS |
Mike Jordan
|
|
|
P.O.C. Chris Root Phone #: ###-#### Inspection requested via web by Dave Daniel
|
BLD-Footing | 5/29/2020 | 5/29/2020 | 5/29/2020 | P | PASS |
Brandon Shaw
|
|
|
this is a pole style structure, need to have the holes inspected, there is not a foundation Phone #: ###-#### Inspection requested via web by Dave Daniel
|
Issue PAID IN FULL permit | | | 5/19/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/19/2020 | | DONE |
|
|
|
|
Telephone call | | | 5/19/2020 | | DONE |
|
|
|
email permits and inspection card to- meridian@clearybuilding.com and croot@clearybuilding.com
|
Telephone call | | | 5/18/2020 | | DONE |
|
|
|
email GC asking to provide us with a RP, waiting for RP to Issue permit
|
Plan assigned to (JAB) Josh | 4/29/2020 | 4/29/2020 | 5/14/2020 | | PASS |
Josh Bogle
|
|
|
05/05 shop, ePlan
|
Routing - PLAN CHECK | 4/29/2020 | | 5/14/2020 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 5/14/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/14/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 5/14/2020 | | DONE |
|
|
|
MET NEED RP
|
Routing - PLANNING | 4/29/2020 | | 5/5/2020 | | PASS |
Leon Letson
|
|
|
|
Intake Approval | | | 4/29/2020 | | PASS |
|
|
|
|
Application received | | | 4/28/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 28 2020 11:13AM
|
Intake Approval | | | 4/28/2020 | | FAIL |
|
|
|
1. Plans must be uploaded as individual sheets.
2. Upload any Planning & Zoning letter(s) of approval where applicable – i.e. Conditional Use Permit (CUP), Planned Unit Development (PUD), Design Review/Historic Permit (DRH), Floodplain (CFH) and/or other approval documents.
3. We cannot accept "PNG" format, The Drawing "Vogt Site Photo" must be in PDF Format, that drawing was deleted please upload a new Site Plan in PDF.
|