Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD20-01465
StatusUnder Review
Name INTEGRITY LLC
Site Address 221 W BOISE AVE
Project NameBeach Addition
Customer Number 
ePlanReviewYes
Description
**PLAN MODIFICATION - Changing roof line to comply with setback requirements - JJN 07/20/20) Permit for a remodel, to include: 240 sq ft addition for new master suite. - All work per plans, notations, attachments, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JJN**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Plan Modification Accepted  8/11/2020 DONE
Plan mod to move master bedroom
BLD-Foundation8/4/20208/5/20208/5/2020AFAIL
DetailsBrandon Shaw
Need Planning approval for 3' setback...
CHANGE STATUS TO (ISS)  7/23/2020 DONE
OVERRIDE  7/21/2020  
Permit Ready to Issue  7/21/2020 DONE
PLAN MOD - MET
Plan assigned to (J_N)7/15/20207/15/20207/20/2020 DONE
DetailsJenny Nelson
plan mod
Routing - PLAN CHECK7/15/2020 7/20/2020 PASS
DetailsJenny Nelson
Routing - PLANNING7/15/2020 7/15/2020 PASS
DetailsSue Cummings
Plan Modification Accepted  7/15/2020 DONE
Reed Peterman called requesting a plan mod for roofline adjustments.
BLD-Foundation6/25/20206/26/20206/26/2020AFAIL
DetailsMike Jordan
wall.. call to meet // Scott ........ Screened Phone #: ###-####. Needs to locate property line or have reduce setback approved by zoning and show soffit protection on plans
BLD-Footing6/15/20206/16/20206/16/2020ANR
DetailsJim Storey
Scott *screened* Phone #: ###-#### control water and dry out. call for reinsp.
Telephone call  6/1/2020 DONE
smqualityrestore@gmail.com informed we need RP
Issue PAID IN FULL permit  6/1/2020 DONE
Inspection Record Card- Bld  6/1/2020 DONE
OVERRIDE  5/29/2020  
Permit Ready to Issue  5/29/2020 DONE
met
Need RP: emailed applicant to let them know
Plan assigned to (J_N)5/28/20205/28/20205/28/2020 DONE
DetailsJenny Nelson
Plan assigned to (JAB) Josh5/11/20205/11/20205/28/2020 DEFR
DetailsJosh Bogle
05/15 addition, ePlan
Routing - PLAN CHECK5/11/2020 5/28/2020 PASS
DetailsJenny Nelson
1st review completed  5/28/2020 DONE
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  5/28/2020 DONE
DetailsJenny Nelson
ESC yes, energy yes
Intake Approval  5/11/2020 PASS
Routing - PLANNING5/11/2020 5/11/2020 PASS
DetailsSue Cummings
Intake Approval  5/4/2020 FAIL
Plan must be uploaded as individual files in the drawings files with file names that include what is on the plan. (example: Site Plan or A1 Site Plan)
Application received  5/3/2020 PASS
Application submitted via PDS Online on May 3 2020 5:50PM
Plan assigned to (J_N)8/11/20208/11/2020   
DetailsJenny Nelson
Routing - PLAN CHECK8/13/2020    
DetailsJenny Nelson