CHANGE STATUS TO (ISS) | | | 8/7/2020 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 8/6/2020 | 8/6/2020 | 8/6/2020 | | DONE |
Brian McGowan
|
|
|
07/30 modification
|
Permit Ready to Issue | | | 8/6/2020 | | |
|
|
|
**DO NOT ISSUE - PLAN MOD**
|
Routing - PLAN CHECK | 7/24/2020 | | 8/6/2020 | | PASS |
Brian McGowan
|
|
|
|
Plan assigned to (JAB) Josh | 7/24/2020 | 7/24/2020 | 7/24/2020 | | DEFR |
Josh Bogle
|
|
|
07/30 modification
|
Plan Modification Accepted | | | 7/24/2020 | | DONE |
|
|
|
taking master bath and second bath (upstairs) and making master bathroom bigger and making second bath into powder room
|
BLD-Framing/Rough-in | 6/29/2020 | 6/29/2020 | 6/29/2020 | P | PASS |
Tony Young
|
|
|
Porsche Phone #: ###-####.. ok to cover
|
Inspection Record Card- Bld | | | 5/21/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/19/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/19/2020 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 5/7/2020 | 5/7/2020 | 5/18/2020 | | PASS |
Josh Bogle
|
|
|
05/13 remodel, ePlan
|
Routing - PLAN CHECK | 5/7/2020 | | 5/18/2020 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 5/18/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/18/2020 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Plans ACCEPTED BY PLAN TECH | | | 5/7/2020 | | DONE |
|
|
|
|
Intake Approval | | | 5/7/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/7/2020 | | DONE |
|
|
|
|
Application received | | | 5/6/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 6 2020 9:25AM
|