BLD-Wall Bracing | 8/10/2020 | 8/10/2020 | 8/10/2020 | P | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-#### Inspection requested via web by Todd Twedt
|
BLD-Footing | 7/22/2020 | 7/23/2020 | 7/23/2020 | P | PASS |
Brandon Shaw
|
|
|
Pat *screened* Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 7/20/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 7/7/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 6/23/2020 | 6/23/2020 | 7/7/2020 | | DONE |
Rob Patrick
|
|
|
plan mod
|
Routing - PLAN CHECK | 6/23/2020 | | 7/7/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/7/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 7/7/2020 | | DONE |
|
|
|
PLAN MOD
|
BLD-Footing | 6/22/2020 | 6/23/2020 | 6/24/2020 | P | NR |
Jim Storey
|
|
|
screened // Pat Phone #: ###-####
|
Plan Modification Accepted | | | 6/23/2020 | | DONE |
|
|
|
Rebekah from CBH requested a plan mod for foundation and site plan
|
Routing - PLANNING | 6/23/2020 | | 6/23/2020 | | PASS |
Sue Cummings
|
|
|
|
OVERRIDE | | | 6/16/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 5/18/2020 | 5/18/2020 | 6/16/2020 | | DONE |
Rob Patrick
|
|
|
2nd Review Complete 06/08 Failed: 05/29 sfd L1 ePlan
|
Issue PAID IN FULL permit | | | 6/16/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/16/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/16/2020 | | 6/16/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/16/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 6/16/2020 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 6/8/2020 | | 6/8/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - PLAN CHECK | 5/18/2020 | | 6/3/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
1st review completed | | | 6/3/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - MECHANICAL | 5/18/2020 | | 5/22/2020 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 5/18/2020 | 5/21/2020 | 5/19/2020 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 5/18/2020 | | 5/19/2020 | | PASS |
Sue Cummings
|
|
|
This lot has the adjacent common lot
|
Routing - Addressing | 5/18/2020 | | 5/19/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/18/2020 | | 5/19/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/18/2020 | | DONE |
|
|
|
|
Intake Approval | | | 5/18/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/18/2020 | | DONE |
|
|
|
|
Application received | | | 5/14/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 14 2020 1:31PM
|