BLD-Energy code compliance | 8/10/2020 | 8/11/2020 | 8/11/2020 | A | PASS |
Tony Young
|
|
|
Please call in advance. Phone #: ###-#### Inspection requested via web by Cole Krueger
|
BLD-Framing/Rough-in | 8/10/2020 | 8/10/2020 | 8/10/2020 | P | PASS |
Tony Young
|
|
|
Please call in advance. Phone #: ###-#### Inspection requested via web by Cole Krueger
|
BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 | P | PART |
Tony Young
|
|
|
Please call in advance. Phone #: ###-#### Inspection requested via web by Cole Krueger,, ok to insulate,, needs engineer approval on drag strut,, also on existing header// verify seal package
|
Plan assigned to (JAB) Josh | 5/19/2020 | 5/19/2020 | 6/15/2020 | | PASS |
Josh Bogle
|
|
|
05/25 remodel, ePlan - 1st done
|
Routing - PLAN CHECK | 6/15/2020 | | 6/15/2020 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/15/2020 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 6/15/2020 | | DONE |
|
|
|
met
|
Issue PAID IN FULL permit | | | 6/15/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/4/2020 | | 6/4/2020 | | FAIL |
Josh Bogle
|
|
|
engineering was incomplete, section views lacked detail
|
1st review completed | | | 5/21/2020 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 5/19/2020 | | 5/21/2020 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan
|
Routing - PLANNING | 5/19/2020 | | 5/19/2020 | | PASS |
Sue Cummings
|
|
|
|
Meeting | | | 5/19/2020 | | DONE |
|
|
|
per Melissa: No Hillside review required. Please do not route to hillside for building permit review. MMJ mjannusch@cityofboise.org
|
Intake Approval | | | 5/19/2020 | | PASS |
|
|
|
|
Application received | | | 5/15/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 15 2020 8:24AM
|
Telephone call | | | 5/15/2020 | | DONE |
|
|
|
called and asked applicant if footprint will change, and he said yes, so sent to hillside.
|